Engineering has signed a contract for the construction of Cakovec solar power plant, which will be located at the premises of the former Agromedimurje farm complex.
This solar power plant, with a connecting power of 8,500 kW, will contain a total of 20,228 monocrystalline modules with a total power of 11,024.26 kWp, and the expected annual electricity generation will amount to 12,730.8 MWh. The contract was signed according to the “turnkey” principle up to the full functionality of the solar power plant, including the obtaining of an operating permit and a permit for continuous operation of the power plant, with the commencement of works planned for mid-April 2024. The completion of Cakovec SPP construction is expected in February 2025.