Enauta Participações S.A. informs that production totaled 157 thousand barrels of oil equivalent (boe) in
June/2024 and approximately 1.3 million barrels in the first quarter, as detailed below.
ATLANTA – First well connection to FPSO Atlanta and Maintenance update on FPSO Petrojarl
In June, FPSO Atlanta anchoring was concluded. On July 4th, the first
producing well and all its service lines connections were completed.
The second producing well connection, which allows start of
production on the new platform, will be concluded in the coming
weeks, according to the operational schedule for the Full Development
System installation.
However, strikes announced by public officials of regulatory agencies
may impact the start of production schedule. On the other hand, the
remaining four producing wells connection shall follow the original
project schedule accordingly.
Given the uncertainty on the schedule for FPSO Atlanta’ start of
operation, Enauta chose to postpone the Early System return of
production of through FPSO Petrojarl for the next two weeks, by
including maintenance items which allow operations extension until
the fourth quarter of 2024.
MANATI – Production resumption updated for the third quarter
Manati remained shut down for equipment adjustments throughout June. The operator updated the
production resumption forecast for the third quarter.