Gresham House Energy Storage Fund Announces Operational capacity reaches 845MW / 1,207MWh

Source: www.gulfoilandgas.com 11/6/2024, Location: Europe

Gresham House Energy Storage Fund plc (LSE: GRID), the UK's largest fund investing in utility-scale battery energy storage systems (BESS), is pleased to announce the energisation of one new project and the energisation of battery duration augmentations on two existing projects adding 55MW and 176MWh of capacity to the operational portfolio. These projects are:

- Elland, a 50MW / 100MWh new project near Leeds, was energised on 1 November.

- Penwortham B, an augmentation to the original Penwortham site, was energised on 30 October, resulting in the project duration increasing to two hours (50MW / 100MWh)

- Nevendon B was energised on 23 October. The augmentation has increased the capacity of the site from 10MW / 7MWh to 15MW / 33MWh.

This increases the operational capacity of the portfolio to 845MW / 1,207MWh from 790MW / 931MWh at 30 June.

In terms of tolling, the Company is also pleased to report that, of the 568MW announced as being contracted into tolling agreements with Octopus Energy, 260MW are now onboarded. Further capacity is expected to enter the agreement shortly, linked largely to operational timings on the remaining portfolio in construction.

Further updates will be provided as projects are commissioned and/or are onboarded into tolling.

Ben Guest, Fund Manager of Gresham House Energy Storage Fund plc & Managing Director of Gresham House New Energy, said:

"These updates will have a positive impact on revenues as more capacity translates into proportionately more revenues while tolling contracts have been struck at levels that remain above current merchant levels, increasing revenue per MW. Five of the seven augmentation projects planned for the year have now been completed, demonstrating the ability these projects have in rapidly bringing new capacity online."

Capital Markets Day

Fund Manager, Ben Guest will set out the framework for the Company's three-year plan through 2027, including indicative targets for MW and MWh capacity, revenues, and EBITDA at the Capital Markets Day on Wednesday 27 November, 2.00-4.00pm (GMT).


Canada >>  12/2/2024 - St-Georges Eco-Mining Corp., is pleased to announce that EVSX Corp, a wholly-owned subsidiary, commenced the installation of one of its three state-of...
Canada >>  12/2/2024 - First Phosphate Corp. ("First Phosphate" or the "Company") is pleased to announce that it has signed a technology license agreement ("TLA") with Prayo...

Hungary >>  12/2/2024 - NGK INSULATORS, LTD. (hereinafter, “NGK”) announces that it has received an order for NAS batteries for storing electric energy from Greenergy Triotec...
United States >>  12/2/2024 - On December 2, 2024, LPO announced a conditional commitment for a loan of up to $7.54 billion to StarPlus Energy LLC to help finance up to two lithium...

Canada >>  11/28/2024 - NEO Battery Materials Ltd., a low-cost silicon anode materials developer that enables longer-running, rapid-charging lithium-ion batteries, is pleased...
Canada >>  11/28/2024 - St-Georges Eco-Mining Corp., is pleased to announce that EVSX Corp, a wholly-owned subsidiary, commenced the installation of one of its three state-of...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.