Comet Ridge Limited Announces Operational Update in Mahalo Gas Hub Projects

Source: www.gulfoilandgas.com 12/6/2024, Location: Not categorized

Comet Ridge Limited (ASX:COI) is pleased to provide the following operational update in relation to its three most significant Mahalo Hub Projects.

Mahalo East (Comet Ridge 100%) - Pilot Production Scheme
Following the recent successful drilling of the Mahalo East 1 vertical well and the Mahalo East 2 lateral well, laboratory analysis for the recovered core from the vertical well is ongoing and continues to show strong gas volumes desorbing from the coal samples. For more information on the drilling conducted, please refer to ASX releases on 10, 21 and 31 October and 11 November 2024. Both of these wells were drilled with the support of the Queensland Government’s Frontier Gas Exploration Grants Program, under which Comet Ridge will receive a $5 million funding allocation.

A smaller completion rig has recently installed production tubing and a downhole progressive cavity pump (PCP) for lifting water out of the vertical well. The production separator, flare and metering skid have been moved from the Mahalo North pilot area and are currently being installed on the Mahalo East 1 well pad. Also being installed is a temporary lined ring tank to collect and manage produced water, when testing starts next month.

Mahalo JV Project (Comet Ridge 57.14%) - Operator enters FEED
The Operator has approved the Mahalo JV Project to commence Front End Engineering Design (FEED). This is a key milestone in moving the project out of the feasibility stage and into FEED, as a pre-cursor to a Final Investment Decision (FID).

Comet Ridge looks forward to working with the Operator on the upstream FEED process to finalise the work program and timetable over the coming weeks.

Mahalo North (Comet Ridge 100%) - Environmental Approvals
Following the Environmental Authority (EA) awarded by the Queensland Government in August, the process for EPBC approval continues through the Federal Government. Comet Ridge’s recent activities have focused on field analysis and sampling to provide information in response to a detailed preliminary data request. It is anticipated the final report from the Company will be submitted early next week now that laboratory analysis of these field samples is being finalised.


United Kingdom >>  1/24/2025 - ITM is pleased to announce that we have been contracted by a European energy company to jointly develop a standard design configuration for a 10MW gre...
United Kingdom >>  1/23/2025 - Technip Energies has been awarded a Front-End Engineering Design (FEED) contract for the proposed new build Combined Cycle Gas Turbine (‘CCGT’) power ...

Estonia >>  1/20/2025 - AFRY has been selected by Enefit Green to deliver front-end engineering design (FEED) services for the 1GW Liivi Bay offshore wind farm in the Gulf of...
Norway >>  1/15/2025 - Capsol Technologies has been awarded an Engineering Services Agreement for a pre-FEED (Front-End Engineering Design) study for the CapsolEoP® (end-of-...

Estonia >>  1/14/2025 - Enefit Green and AFRY signed a contract to deliver the Front-End Engineering Design (FEED) services for the 1GW Liivi Bay offshore wind farm in Estoni...
Norway >>  1/13/2025 - Multiconsult Norge AS, in collaboration with subcontractors Aker Solutions AS and fully owned subsidiary LINK Arkitektur AS, has been awarded a contra...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.