MISO Board Approves Historic Transmission Plan to Strengthen Grid Reliability

Source: www.gulfoilandgas.com 12/12/2024, Location: North America

Today, the MISO Board of Directors unanimously approved the largest portfolio of transmission projects in the nation’s history. The 488 projects span more than 5,000 miles across 15 states in the MISO footprint and include local reliability and growth projects, the Long Range Transmission Planning (LRTP) Tranche 2.1 portfolio of projects and the Joint Targeted Interconnection Queue (JTIQ) projects with Southwest Power Pool.

“This was truly a significant effort that required coordination and collaboration with our stakeholders, our neighboring grid operators and MISO staff,” said MISO’s Chief Executive Officer John Bear. “The energy landscape is quickly transitioning, and we must work with urgency to implement the changes that ensure reliability today and in the future.”

The 2024 MISO Transmission Expansion Plan (MTEP) includes the following:

Local Reliability – 459 projects totaling 932 miles to support reliability in all 15 states across the MISO region. The $6.7B investment will improve infrastructure and meet load growth needs at the local level.
LRTP Tranche 2.1 – 24 projects totaling 3,631 miles for regional projects in MISO’s Midwest subregion (Illinois, Indiana, Iowa, Michigan, Minnesota, Missouri, North Dakota, South Dakota and Wisconsin) and includes a 765kV backbone. The $21.8 billion portfolio has a cost-to-benefit ratio of 1.8-3.5 with benefits potentially exceeding $72 billion.
JTIQ – five projects totaling 490 miles to enable generation on the MISO/SPP seam (Iowa, Kansas, Minnesota, Missouri, North Dakota and South Dakota). The $1.6 billion investment will enable 28 GW of new generation.

“While the work we do to study and recommend projects that strengthen local transmission is always important in annual MTEP planning cycles, the development of the Tranche 2.1 and JTIQ portfolios was history-making and game-changing work,” said Aubrey Johnson, MISO’s vice president of system and resource planning. “The JTIQ Portfolio enables future generator interconnections that are needed on the SPP-MISO seam and LRTP Tranche 2.1, building off Tranche 1, provides a solid foundation for the grid for the next several decades.” MISO followed an extensive stakeholder process, facilitating more than 300 meetings and capturing feedback to arrive at a robust Tranche 2.1 portfolio that delivers benefits exceeding costs. LRTP is a key part of the Reliability Imperative — the shared responsibility of states, utilities, members and MISO to address the complex challenge to electric reliability in the region, including generation fleet change, increasing extreme weather events and other factors.


Australia >>  1/23/2025 - The Australian Energy Market Commission (AEMC) has made a final rule to help secure South Australia's electricity supply this summer. The decision all...
Japan >>  1/23/2025 - Global IT corporation FPT, Chugoku Electric Power, one of Japan’s leading utility providers, and Enecom, a prominent technology and communication inno...

Spain >>  1/23/2025 - Zelestra, a global, multi-technology, customer-focused, renewable energy company, has closed a ten-year power purchase agreement (PPA) in Spain with a...
United Kingdom >>  1/23/2025 - On 7 March 2024, SSE plc raised Connection and Use of System Code (CUSC) Modification Proposal CMP432: Improve “Locational Onshore Security Factor” fo...

United Kingdom >>  1/23/2025 - Botein Bess Ltd hereby gives notice that it has made an application to the Gas and Electricity Markets Authority for an electricity generation licence...
United States >>  1/23/2025 - Neara, the first AI-powered predictive modeling software platform for critical infrastructure, released survey findings from 2,000 US consumers on ene...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.