The heater facility project at the Brunsbüttel LNG Terminal, operated by DET Deutsche Energy Terminal GmbH, continues to progress according to schedule.
Under our ongoing contract with Gasfin, MT Group is currently focused on concreting the base plates, with 3 out of 6 already successfully completed – a key milestone in the structural foundation phase.
In Lithuania, piping prefabrication has now been successfully finalized. Materials are being delivered to both the painting facility and the construction site, ensuring seamless workflow continuity across borders.
On-site, mechanical works have officially commenced. Installation teams are fully mobilized, and preparations are in place for the welding of piping, equipment installation, and structural steel assembly, all set to begin next week.
Our sincere thanks to all teams involved for their dedication and coordination in driving this complex project forward.