Chariot Updates on Rig Negotiations for Namibia Drilling

Source: www.gulfoilandgas.com 11/30/2011, Location: Africa

Chariot Oil & Gas Limited, the Africa focused oil and gas exploration company, provides an update with regard to its drill rig contract negotiations. As reported in the Interim statement on 24 October 2011, the Company has been aggressively pursuing various rig options for drilling its Tapir South prospect (located in Northern Block 1811 A offshore Namibia), which included an option that would have enabled the well to spud prior to the 2011-year end.

As Chariot noted previously, the market for deepwater rigs has tightened markedly, making it more challenging to secure an appropriate rig to carry out a one-well programme in Namibia without paying a significant premium.

As mentioned in the Interim statement, Chariot's Tapir South prospect is drill ready - all long lead items have been delivered, all service contracts signed, the support base secured and the drill permit granted. However, the rig anticipated to be available for the Q4 2011 spud has been contracted by another operator for a longer programme. As a result of this change in programme the rig will no longer be coming into the area in the requisite timeframe.

The Company is in active negotiations regarding a number of other available rigs and now expects to spud the Tapir South exploration well in Q2 2012. This timing is subject to ongoing negotiations and further to a rig contract being formally signed, the Company will update the market with the anticipated spud date.

Paul Welch, Chief Executive of Chariot Oil and Gas, said:
"Whilst it is disappointing not to have secured a rig to drill Tapir South this year, we continue to negotiate other options at commercially attractive rates. The rig market is tight but also very dynamic and whilst we are looking to drill as soon as possible next year, we need to manage this to optimise our drilling programme going forward.

"We are looking forward to 2012 which should be a pivotal year for Chariot with an exploration well in each of our Northern and Southern blocks expected, plus the results of the 3D seismic survey currently underway on our Central blocks. We continue to pursue our longer term strategy of drilling 4-5 wells through to end 2013 and will report on further progress as soon as possible."


Singapore >>  6/29/2022 - The Deepwater Atlas, the first drillship of the eighth generation in the world, was successfully delivered by Sembcorp Marine Ltd to Transocean's subs...
Bermuda >>  6/27/2022 - In order to sell the "Tivar," "Huldra," and "Heidrun" (collectively referred to as the "Transaction Rigs"), three high-specification units being built...

United Kingdom >>  6/23/2022 - Noble Corporation has entered into an asset purchase agreement to sell five jackup rigs for $375 million to a newly formed subsidiary ("Buyer") of She...
Saudi Arabia >>  6/22/2022 - The contract extensions for the AOD I, AOD III, and West Callisto for work offshore in the Arabian Gulf have been awarded to Seadrill Limited ("Seadri...

United Kingdom >>  6/22/2022 - In addition to our press release from June 9, 2022, Awilco Drilling Plc announces that the previously mentioned sale of the drilling rig WilHunter has...
Norway >>  6/21/2022 - The Petroleum Safety Authority Norway (PSA) has given an order to Equinor after an audit of that company and KCA Deutag (KCAD) as well as their develo...

Related Categories: General  Rig Equipment  Rig Operators  Rigs, Coring & Exploration 

Related Articles: General  Rig Equipment  Rig Operators  Rigs, Coring & Exploration 


Gulf Oil and Gas
Copyright 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.