McDermott Awarded North Dome & PDM Projects for Aramco

Source: www.gulfoilandgas.com 11/5/2012, Location: Middle East

McDermott International, Inc. announced that one of its subsidiaries has recently been awarded two projects by Saudi Aramco in the Abu Safah, Marjan and Safaniya fields in the Arabian Gulf.

The two projects consist of six topsides and a bridge that connects to the existing Marjan facilities. In addition, the project will require other associated modifications and brownfield work. The combined total weight of the structures will exceed 4,000 metric tonnes.

The North Dome project, which was issued under the existing Long Term Agreement and is included in McDermott’s third quarter 2012 backlog, comprises procurement, construction and installation of two wellhead decks for Abu Safah and Marjan, and an auxiliary platform and access bridge for Marjan.

The second project, also issued under the existing Long Term Agreement, was included in McDermott’s 2012 second quarter backlog and comprises procurement, fabrication, transportation and installation of three electrified production deck modules (PDM’s) in the Safaniya and Marjan fields. McDermott’s Jebel Ali fabrication facility will construct the platforms, while vessels from McDermott’s global fleet will be used to install the facilities.

“We will be executing both projects using engineering, project management and procurement resources from our Al-Khobar, Saudi Arabia office. Our In-Kingdom activities continue to grow as we ramp up this Engineering office and our recruitment efforts, to position McDermott for current and future project requirements,” said Stewart Mitchell, Senior Vice President and General Manager, Middle East, Caspian and North Sea for McDermott.

Offshore Platforms News in Saudi Arabia >>

United Kingdom >>  2/20/2019 - Two normally unmanned installations which used to produce gas in Morecambe Bay will be decommissioned under plans to be submitted by Spirit Energy. ...
Iran >>  2/10/2019 - Phases22-24's director, FarhadIzadjoo, announced that the second topside of this project sailed from SADRA yard to its location. Satellite platform 24...

Iran >>  2/8/2019 - The deputy of marine pipeline project for phase13, Mohsen Azizi, announced that the infield pipelaying operations were completely carried out from the...
Iran >>  2/1/2019 - Platform 24A, the second platform of phases 22-24 of developing South Pars gas field, was shipped on Thursday to be installed on its designated offsho...

Related Categories: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 

Related Articles: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 


Saudi Arabia Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 |

Oil & Gas Projects in Saudi Arabia >>

More News

Related Links

Gulf Oil and Gas
Copyright © Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.