Lukoil Continues Development at V.Filanovsky Field

Source: www.gulfoilandgas.com 7/23/2013, Location: Asia

Offshore operations have started in Astrakhan to transport two offshore facilities built by order of LUKOIL for field infrastructure development at the Vladimir Filanovsky field located in the Caspian Sea. They are substructures for the living quarters module platform (LQP-1) and riser block (RB).

These facilities will soon be towed to the field and affixed to the seafloor in the immediate vicinity of the substructures for the soon to be completed ice-resistant stationary platform (IRP-1).

Two substructures for the LQP-1 with a total weight of more than 2,000 tons are affixed to the seafloor with 16 piles that will be hammered into the seafloor60 meters down. The RB substructure is fixed with 8 pillars with a diameter of approximately 2 meters.

The offshore facilities are assembled by means of a Transport and Installation Barge (TIB), which has a crane with a loading capacity of 400 tons.

The assembly of the substructures for IRP-1, LQP-1 and RB at the field will be followed by the assembly of the substructures for the central processing platform (CPP).

Assembly of topsides for IRP-1, LQP-1, RB and CPP, as well as the catwalk bridges to connect them is scheduled for 2014.

All of the offshore facilities for the Vladimir Filanovsky field are manufactured by Astrakhan’s shipbuilding enterprises by order of LUKOIL.

Commercial drilling at the Vladimir Filanovsky field is scheduled to begin in 2014. Oil production is to begin by the end of 2015.

Offshore Platforms News in Russia >>

United Kingdom >>  4/9/2019 - Unique Group, one of the world’s leading integrated subsea and offshore solution providers, has designed and developed its first Unmanned Surface Vehi...
Thailand >>  3/26/2019 - Norwegian offshore service and supply ship company Solstad Offshore has been awarded a contract by Ophir Energy to perform an offshore installation of...

Norway >>  3/22/2019 - Prosafe has agreed with Aker BP ASA to restructure the remaining seven one-month options for the Safe Scandinavia at the Ula platform in the Norwegian...
Norway >>  3/22/2019 - Three days – that’s what it took to lift four of the last pieces in the Johan Sverdrup puzzle into place – the two final platform topsides, a bridge a...

Related Categories: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 

Related Articles: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 


Russia Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 |

Oil & Gas Projects in Russia >>

More News

Related Links

Gulf Oil and Gas
Copyright © Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.