NORTH STOCKYARD PROJECT, WILLIAMS COUNTY, NORTH DAKOTA
Blackdog 3-13-14H (SSN WI 25.03%)
Currently the 6 inch lateral portion of the well is being drilled at a depth of 17,906 feet into the
Middle Bakken. The forward plan is to drill the Blackdog to a total depth of 19,987 feet.
This well will be a middle Bakken lateral and is the infill location between the Rodney 1-14H well
(SSN WI 27.18%) and the Sail and Anchor 1-13-14HBK well (SSN WI 25.03%).
Frac operations in the Blackdog well are expected to take place following the Christmas Holiday.
Coopers 2-15-14HBK (SSN WI 27.7%),
Fracture stimulation operations on the Coopers well finished on December 11th with the placement
of 2.7 million pounds of proppant over 22 stages in the 6,393 foot lateral that was drilled in the
Middle Bakken.
Tooheys 4-15-14HBK (SSN WI 27.7%),
The 24 stage sliding sleeve fracture stimulation was completed on the Tooheys over the weekend.
A total of 2.3 million pounds of proppant was pumped into the well over 24 stages along the 6,740
foot lateral that was drilled in the Middle Bakken.
Little Creature 3-15-14HBK (SSN WI 27.7%),
The Little Creature well has been prepared for frac operations, which are expected to commence
after the Christmas Holiday.