Gazprom Completes Testing on Second Well at Badra

Source: www.gulfoilandgas.com 3/13/2014, Location: Middle East

In February 2014, Gazprom Neft successfully completed testing on its second well at the Badra field, operated by the Company. Three tests on the well delivered average daily flow rate of 10,000 barrels of oil, in line with forecasts.

Completed testing on two wells (test launch of the first well was concluded in December 2013) will enable the Company to begin commercial oil production at the Badra field over the next few months. Drilling work is continuing on a third well and drilling rigs are being mobilised to drill six additional wells as part of the contract signed in 2013 with Chinese company ZPEC.

Laying and testing of the oil pipeline from Gharraf oilfield, connecting it to the main Iraqi pipeline system, was completed in February. Construction of the first phase of the central gathering station (CGS), with 60,000 barrel per year oil capacity, is almost completed. Works has also started on establishing a gas processing facility with a capacity of 1.5 billion cubic metres per year.

The Badra oil field is located in Wasit Province in Eastern Iraq. According to preliminary estimates, geologic reserves at the Badra field amount to 3 billion barrels of oil. The contract with the Iraqi government for development of the oil field was signed in January 2010 upon completion of a bid process in December 2009. The winning bid was submitted by a consortium of companies consisting of Gazprom Neft, KOGAS (Korea), PETRONAS (Malaysia), and TPAO (Turkey).

Gazprom Neft’s share in the project is 30 percent, while KOGAS has 22.5 percent, PETRONAS has 15 percent, and TPAO has 7.5 percent. The share of the Iraqi government, represented in the project by the Iraqi Oil Exploration Company (OEC), is 25 percent. Gazprom Neft is the project operator.

The Badra oil field development project is designed to last twenty years, with a possible extension of five more years. By 2017, the production volume is forecast to reach 170,000 barrels of oil per day (approximately 8.5 million tonnes per year), and remain at that level for seven years.

For more information about related Opportunities and Key Players visit Iraq Oil and Gas Projects


Colombia >>  6/27/2022 - The Rio Cravo Sur-1 ("RCS-1") well testing findings on the Tapir Block in the Colombian Llanos Basin are now available, and Arrow Exploration Corp. (A...
Suriname >>  6/21/2022 - The flow test results from the Krabdagu exploration well (KBD-1) on Block 58 offshore Suriname were released today by APA Corporation (APA). APA Surin...

Egypt >>  6/13/2022 - SDX Energy Plc (SDX) is pleased to announce the completion of drilling at the MSD-24 infill development well on the Meseda field in its West Gharib co...
Suriname >>  6/13/2022 - Results from recent drilling operations on Suriname Block 53 were reported by APA Corporation (APA). The operator, APA Suriname, has a 45 percent work...

United States >>  6/10/2022 - The Company provides updates on its Saltfleetby commissioning schedule. The procedure has been handed over to commissioning specialists now that all o...
Canada >>  6/8/2022 - Southern Energy Corp. is excited to announce successful early flowback results from the first well of the three-well horizontal padsite located in the...

Related Categories: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 

Related Articles: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 


Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.