Oilex Ltd is pleased to announce that Stage 1 fracture stimulation (frac) has been successfully completed. Subsequently, Cambay-77H started unaided flowback with indications of gas at surface within 24 hours while other operations were ongoing.

Since the previous announcement on 24 June 2014:

- Stage 1 Micro frac and Data frac were completed
- Stage 1 was treated with a total of ~6,000 bbls of frac fluid and ~136 tonnes of sand
- Elevated bottom hole pressure of 5,000 psi was measured
- The well started to flowback unaided and gas was detected at surface shortly after Stage 1 frac
- 2 isolation plugs were set between Stage 1 and 2 because the first failed to seal
- Stage 2 perforations were successful completed

Subsequent to Stage 1 activities, gas was detected at surface and elevated overpressure of ~5,000psi was measured indicating a pressure increase of 670psi. The original reservoir pressure of ~4,330psi was interpreted from the micro frac programme. This is consistent with Cambay-76H as highlighted in the Quarterly Report to Shareholders 30 September 2012.

During the system wide pressure test to 9,300psi prior to the Stage 2 frac, a leak developed in the “frac tree”. The decision was taken to replace the faulty component(s) with spare components pre-positioned at the well site, before proceeding further with fracture stimulations. Whilst these operations are complex and are currently in progress, they are essential to maintaining the philosophy of risk minimisation.

Managing Director of Oilex, Ron Miller, said;
“We are pleased with the initial response of the well to “fraccing” after Stage 1. Importantly, the elevated over-pressure of ~5,000psi appears to be a very positive result. The delay associated with changing frac tree components is unfortunate but has been partially mitigated. Oilex looks forward to re-commencing frac ops as soon as possible followed by the flowback and clean-up in a safe manner for all personnel.


Norway >>  8/12/2022 - Aker BP ASA, operator of production licence 941, has concluded the drilling of wildcat well 6507/3-15.

The well was drilled about 14 km nor...

Norway >>  8/9/2022 - The Petroleum Safety Authority Norway has given Equinor consent for exploration drilling in block 6507/8 in the Norwegian Sea.

Operator: E...


Guyana >>  8/5/2022 - The drilling of the Beebei-Potaro exploratory well, located in the Kanuku licence, off the coast of Guyana, has been finished, according to Tullow Oil...
Australia >>  8/4/2022 - - 21 stages were stimulated, which is the greatest number of stimulation stages in a single well in the Beetaloo to date
- Delivered 927m of st...


Romania >>  8/4/2022 - Serinus Energy plc ("Serinus") (SEN), is pleased to announce that the drilling of the Canar-1 exploration well in Romania commenced.

...

Norway >>  8/3/2022 - The Norwegian Petroleum Directorate (NPD) has granted Equinor a drilling permit for well 6507/8-11 S in production licence PL 124.

Related Categories: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 

Related Articles: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 


Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.