McDermott Completes Kepodang Platform Installation Offshore Indonesia

Source: www.gulfoilandgas.com 1/8/2015, Location: Asia

McDermott International, Inc. (McDermott) has completed the installation of a 3,086-ton central processing platform (CPP) topside using the tight-slot float-over method in the Kepodang gas field, Muriah Working Area, offshore Indonesia for PC Muriah Ltd, a wholly-owned subsidiary of PETRONAS. This brings the installation of all structures for the Kepodang project to a close.

McDermott commenced operations on this fast-track project, one month after the contract was awarded, in January 2013.

“The overall success of this project was made possible by the smart engineering of the float-over sequence to position the CPP topside next to an existing wellhead module already installed on the jacket at the installation site,” said Hugh Cuthbertson, Vice President and General Manager, Asia Pacific. “Our global team of in-house engineering experts, high performance fabrication at our Batam, Indonesia yard and our strong supplier relationships in Indonesia were our key differentiators. We are also proud to be recognized by PETRONAS as “Best Contractor HSE Performer 2013” for our exemplary project safety record.”

The project scope included procurement, construction, installation and commissioning of the CPP topside and jacket, a wellhead module, a wellhead platform and jacket, 1.7-mile-long 10-inch diameter infield flowline, and installation of remote control facilities at an onshore receiving facility. The total weight of overall facilities is close to 11,000 tons.

The Kepodang field is located approximately 112 miles northeast of Semarang, Central Java, in water depths of up to 230 feet, and is expected to supply gas to the Tambak Lorok power plant in Semarang, Central Java.

Offshore Platforms News in Indonesia >>

Iran >>  1/12/2019 - The first platform belonging to the phases22-24 started up with the capacity of 500 million cubic feet a day. In order to supply the gas required for ...
Iran >>  1/7/2019 - The second deck belonging to phases22-24 was loaded out and now is ready to sail out. The first satellite deck for phases22-24 which is called 24A, we...

United Arab Emirates >>  12/27/2018 - Drydocks World, a leading marine, onshore and offshore service provider to the shipping, oil, gas and renewable energy sectors, has completed the Rash...
United Kingdom >>  12/26/2018 - When the Ninian Central oil production platform was towed out of Loch Kishorn in May 1978, at just over 600,000 tonnes it was the largest concrete str...

Related Categories: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 

Related Articles: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 


Indonesia Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |

Oil & Gas Projects in Indonesia >>

More News

Related Links

Gulf Oil and Gas
Copyright © Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.