Phase 19 Gas Extraction from South Pars Field Reach 42 mcm

Source: www.gulfoilandgas.com 12/12/2016, Location: Asia

The managing executer of phase 19 of South Pars reported of the increase in the phase gas production and stated that with the operationalization of 19A platform, the daily gas extraction of the phase from the South Pars would be increased to 42 million cubic meters per day.

As reported by the public relations of Pars Oil and Gas Company (POGC), HamidrezaMasoudi stated that currently and only of platforms 19A, 19C, and SPD2, about 42 million cubic meters of rich sour gas are extracted from the South Pars common field which sent to the refineries of the mentioned phase.

The managing executer of phase 19 also commented about the production of the sweet gas in the sweetening rows of the phase.He announced that the rows 1, 3, and 4 are in the operationalization tropic and about 37 million cubic meters of sweet & processed gas would be injected to the 6th line after finalizing the refining processes.

Masoudi announced the production of more than 5 million barrels of gas condensates in the phase and stated that 4.5 million barrels of the same product have been exported to the target markets.

The managing executer of phase 19 pointed to the full operationalization and finalization of gas receipt units in the refinery and added that the available gas condensates of sour gas of the platforms are categorized and transmitted to the gas condensates stabilization unit and after being processed, the product would be kept in gas condensates storage tanks.

He stated that the mentioned units are in the production and added: “one of the compressors belonging to the gas condensates unit has been put in the production and the other compressor is ready for being operationalized”.

Pointing to the great records in the phase 19 of South Pars, he stated that setting up and production of gas from 3 platforms with the total capacity of 1.5 billion cubic feet, the fastest installment record, setting up and production of gas from platform 19(within 70 days), and 3 sweetening rows within a 7-months period have been unprecedented since South Pars beginning.

The executer of phase 19 counted the weekly production of gas in this phase as 254 million cubic meters and stated that about 3.2 billion cubic meters of gas have been produced since the sweet gas production activities.

Announcing that the first row of Butane and Propane of phase 19 would be operationalized by December mid, Masoudi stated that with the finalization of two trains of LPG, 2800 tons of Propane and Butane would be produced in this phase each day.

He added: “With the made schedule, it is prognosticated that the last remained platform of phase 19 with the extraction capacity of 500 million cubic feet of gas would be loaded from the industrial yard of IOEC in Khoramshahr by January 2017 and its operationalization procedures would be done a week after its installment procedures in March”.

Pointing to the environmental obligations, the managing executer of the phase 19 of South Pars stated that the hired procedures in order to reduce the gas burning in this phase have been notable. He added: “With the operationalization of the Off-Gas compressors of the second row of gas condensates stabilization units & the Regeneration compressors of 1st, 2nd and 4th rows of sweetening, the daily waste and gas burning of 4 million cubic meters of gas in this phase has been avoided.

Masoudi emphasized on the efforts made by the employer and contractor of the development project of phase 19 in reducing the pollution of gas-burning in the phase and claimed that two rows of the Sulfur recovery unit would be operationalized fully by January.


Norway >>  7/6/2022 - A number of fields on the Norwegian Continental Shelf now have revised production licences authorised by the Ministry of Petroleum and Energy (NCS). I...
Australia >>  7/4/2022 - Jadestone Energy plc, an independent oil and gas production company focused on the Asia-Pacific region, provides the following update on operations at...

United Kingdom >>  7/4/2022 - IOG plc, the Net Zero UK gas and infrastructure operator focused on high return projects, has released an updated Investor Presentation incorporating ...
Kuwait >>  6/30/2022 - Dr. Muhammad Abdul Latif Al-Fares, His Excellency the Deputy Prime Minister, Minister of Oil, and Minister of State for Council Affairs, led the State...

Kuwait >>  6/30/2022 - Today, Thursday, the members of the (OPEC +) coalition decided to increase output by 648,000 barrels per day in August. Following the 30th ministerial...
Norway >>  6/30/2022 - The authorities have granted consent to start production from the Nova field in the North Sea. Nova will be developed with two seabed templates, one f...

Related Categories: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  Food Supplies  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Unskilled Labors  Utility Systems  Waste Disposal  Water Supply Services  Welding Products/Services 

Related Articles: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Utility Systems  Waste Disposal  Water Supply Services  Welding Products/Services 


Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.