Urals Energy announces update on the development of Dulisma field

Source: www.gulfoilandgas.com 4/15/2008, Location: Asia

Urals Energy announced an update on the development of the Company’s Dulisma field, East Siberia. As part of the ongoing field development plan, the Company has completed the drill stem test of the vertical pilot hole of appraisal well #105. Following positive flow results, well logging is being conducted to thoroughly appraise the reservoir prior to drilling the planned horizontal well. Final completion of well #105 and hook up to production is expected by the beginning of June. Until such time as the Dulisma field is hooked up to ESPO, production from the field will be evacuated by a temporary pipeline and trucks.

Rig Delivery and Field Construction
Earlier this month, Urals took delivery of its second newly built rig from China. This was done on schedule and now allows the Company to begin production drilling with 2 rigs for the remainder of the year. A further two rigs are planned to be mobilized for next winter.

Significant progress has also been made with construction of the field facilities. Preparatory work for the Central Processing Facilities has been completed and piling for key equipment and buildings is now underway. Right of Way clearance and preparation for the pipeline connection to Transneft’s ESPO system is approximately half complete and all the required linepipe has been stockpiled at each end (Dulisma field and Nadezhdinsk ESPO tie-in point), as well as at an interim station at the river Tunguska. At present, 14 km of line has been welded from the Dulisma end and double jointing operations have commenced at Nadezhdinsk.

Overall, the Company has spent about $32 million of its own money to finance Dulisma development in 2008 to date. Following the announcement of well #105’s drill stem test, the remaining $140 million tranche of the Sberbank Dulisma development loan will now become available for drawdown, in several installments against an agreed schedule for development of the field.

Design work on the remaining facilities, including the Central Transfer Facility at the ESPO connection, is being finalized and tendering for construction will take place in May with mobilization planned for early Q3 when weather conditions are more suitable.

The Company remains on track to begin exporting oil in early Q2 2009 into the ESPO system which reportedly is now being partially filled from Taishet and is planned to receive line fill from the Talakan field later this year.

The Company continues to make progress on the disposal of its non-core assets and will provide further details when appropriate.

Drilling News in Russia >>

Ukraine >>  2/25/2021 - Enwell Energy plc, the AIM-quoted oil and gas exploration and production group, is pleased to announce the results of the SV-25 well and the spudding ...
Norway >>  2/19/2021 - The Petroleum Safety Authority Norway (PSA) has given Aker BP consent to use Maersk Invincible to drill well 2/8-IF-16 on Valhall Flanke Nord. ...

United States >>  2/19/2021 - 88 Energy Limited ("88 Energy", 88E) provides the following update related to its operations on the North Slope of Alaska. ...
Norway >>  2/18/2021 - Drilling operations on the Chrysaor-operated Jerv exploration well 15/12-25 commenced today 18th February. The well, in production licence PL973, targ...

United States >>  2/17/2021 - Mosman Oil and Gas Limited the oil exploration, development and production company, announces an update on operations in the US.

Stanley...

Australia >>  2/15/2021 - - WE4 first intermediate hole section reaches final section depth of 2,635m.
- Casing is being run and will be cemented in place.
- Hydroca...


Related Categories: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 

Related Articles: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 


Russia Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 |

Oil & Gas Projects in Russia >>

More News

Related Links

AZ BD BN CN GE HK ID IN IR JP KH KR KZ MM MN MY PG PH PK RU SG TH TJ TM TW UA UZ VN
Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.