First Sign of Johan Sverdrup Emerging Offshore

Source: www.gulfoilandgas.com 7/31/2017, Location: Europe

Last week the jacket for the Johan Sverdrup riser platform was installed by Thialf crane vessel owned by Heerema Marine Contractors (HMC). Weighing a good 26,000 tonnes the jacket is the largest on the Norwegian continental shelf (NCS).

The jacket is stretching 140 metres from the seabed, where it covers an area measuring 94 times 64 metres. It is attached to the seabed by 24 poles weighing more than 9000 tonnes in total.

“This is a special milestone for us, because it is the first visible sign of the Johan Sverdrup field. I am happy that the installation has been carried out safely and fully in line with the plan. We are now looking forward to the next steps of this industrial adventure and the long line of major operations awaiting us. We have already done a lot of work on and below the seabed, and in the time ahead we will gradually become more visible above the sea surface as well,” says Kjetel Digre, project director for Johan Sverdrup.

Head of transport and installation on Johan Sverdrup Thor Kr?kenes has followed the installation of the jacket that was delivered by Kv?rner Verdal.

“The execution of the work has simply been a feat of engineering. It took a lot of good work and detailed planning to prepare the careful lowering of the jacket onto the seabed without any unforeseen incidents,” says Kr?kenes.

The topside is scheduled for installation next year, and production from the field is to start at the end of 2019.

Plateau production is estimated at 40% of NCS oil production. Expected field life is 50 years and the ambition is a world class recovery rate of 70%. Recoverable resources are estimated to be between 2 and 3 billion barrels of oil equivalent.


United Kingdom >>  6/22/2022 - Shell has granted a multi-million pound contract to Bureau Veritas (BV), a global leader in testing, inspection, and certification, to provide verific...
United Kingdom >>  6/17/2022 - It is the end of an era with the removal of the topsides from Fairfield Energy’s Dunlin Alpha. Heerema Marine Contractors and AF Offshore Decom operat...

United Kingdom >>  6/15/2022 - The Safe Boreas has been contracted by a UK client to undertake gangway operations in support of a platform shutdown in the UK North Sea.

T...

Norway >>  6/14/2022 - The Petroleum Safety Authority Norway (PSA) has carried out an audit of Repsol Norge (Repsol) and their planning and follow-up of the removal of the s...

Norway >>  6/14/2022 - The Petroleum Safety Authority Norway (PSA) has carried out an audit of Equinor and their follow-up of measures after investigation of the causes of t...
Norway >>  6/9/2022 - Pioneering Spirit is back in Stord, Norway to deliver multiple decommissioned platform facilities removed from the North Sea’s Valhall field complex, ...

Related Categories: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 

Related Articles: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 


Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.