Source: www.gulfoilandgas.com 10/16/2017, Location: North America

From 1 September 2016 to 25 August 2017 we conducted an audit of ExxonMobil's activities relating to module-based drilling facilities and permanent plugging and abandonment of the wells at the Jotun B facility.

The activity involved Halliburton, Petroleum Well Service, Aker MHWirth and Aker Solutions and several other drilling and well service companies on board the Jotun B facility.

Objective
The objective of the audit was to verify the companies' management systems and technical solutions for meeting the regulatory and standards requirements. The direct purpose was to contribute to the potential for reducing OHAS, environmental and major accident risks to the greatest possible extent.

Result
No non-conformities were identified.

Eight improvement points were identified in connection with:

- Risk register
- Maintenance
- Data transfers
- Installations, systems and equipment
- Manning and competence
- The safety representative role
- Lifting equipment
- Well control

ExxonMobil has been given a deadline of 1 November 2017 to report on how the improvement points will be addressed.


Egypt >>  5/18/2022 - SDX Energy Plc (SDX) is pleased to announce the spudding of the MSD-24 infill development well on the Meseda field. This well is the fourth in a fully...
Australia >>  5/16/2022 - Highlights
- Drilling of Glenaras 28 complete
- Well encountered 27m of gassy coals
- Steps underway to mitigate impact of further uns...


United Kingdom >>  5/13/2022 - UK Oil & Gas PLC has announced that the North Sea Transition Authority (formerly the Oil and Gas Authority) has granted a one-year extension to the ag...
Australia >>  5/12/2022 - Western Gas has provided an operational update on the drilling of the Sasanof-1 exploration well and will issue further updates upon the completion of...

Norway >>  5/12/2022 - Aker BP ASA, operator of production licence 685, has concluded the drilling of wildcat well 35/4-3.

The well was drilled about 20 kilometre...

Tunisia >>  5/12/2022 - Serinus Energy plc (“Serinus”) (SENX) is pleased to announce its interim results for the three months ended 31 March 2022. ...

Related Categories: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 

Related Articles: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 


Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.