Tower Resources plc, the AIM-listed oil and gas company with a focus on Africa, is pleased to provide an update on operations on the Thali block in Cameroon.

As previously disclosed, Tower is in the final stages of planning the NJOM3 well, which will be drilled to a total depth of 1,100 metres intersecting at least three reservoir zones already identified by the NJOM1B and NJOM2 discovery wells drilled on the Njonji structure by the previous operator Total. The well is designed to confirm the greater reservoir thicknesses observed on the reprocessed 3D seismic in the up-dip area of the structure, and also evaluate additional reservoirs that were not present in the areas where Total's wells are located. The NJOM3 well is designed to supplement Total's well data with a suite of measurement and logging tools and drill stem test ("DST") flows to surface. The Company's intention is then to suspend the well with a view to subsequent completion as one of four initial production wells on the structure, as envisaged in the Reserve Report prepared by Oilfield International Limited (OIL) on 30 September 2018. This first phase of development envisaged by the Reserve Report, aiming to exploit the 2C contingent resources (Pmean 18 million barrels oil, gross) already identified in the structure, aims to provide significant production to Tower in 2020.

Since the Company's last update, the Company has received additional data from the original Total wells at NJOM1 and NJOM2, which indicate that further site preparation work will be required before the rig is moved to site. Therefore the Company has agreed with Vantage to move the planned mobilisation of the Topaz Driller to July 2019 instead of late May 2019, in order to allow sufficient time for the additional site preparation work to be completed. This is still within the original date range contemplated by the rig contract, and well within the license extension period agreed last year.

For more information about related Opportunities and Key Players visit West Africa Projects

Drilling News in Cameroon >>

Egypt >>  6/3/2019 - Rockhopper Exploration plc, the oil and gas company with key interests in the North Falkland Basin and the Greater Mediterranean region, is pleased to...
Norway >>  5/24/2019 - MOL Norge, operator of production licence PL 539, is in the process of concluding the drilling of wildcat well 3/7-11 S. The well was drilled about 7 ...

Australia >>  5/21/2019 - JV partner Carnarvon Petroleum has provided an update on the drilling of the Santos-operated Dorado-2 well. Since the last report the 12-1/4 hole has...
Egypt >>  5/21/2019 - Dana Gas PJSC, the Middle East's largest regional private sector natural gas company, has commenced drilling operations on 20 May at its Merak-1 well,...

Australia >>  1/29/2019 - JV partner Carnarvon Petroleum has announced that operator Santos will drill the Roc-South-1 exploration well in 2019. The well will be drilled immedi...
Azerbaijan >>  1/29/2019 -  SOCAR conducted over 160,000 meters of drilling work in the year1 ...

Related Categories: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 

Related Articles: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 


Cameroon Oil & Gas 1 >>  2 | 3 |

Oil & Gas Projects in Cameroon >>

More News

Related Links

Gulf Oil and Gas
Copyright Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.