Tulip Oil Netherlands Offshore, a wholly owned subsidiary of Tulip Oil Holding, is pleased to announce the latest quarterly Q10 Project update.

Initial gas production from the well Q10A-01 started on February 15, 2019. The Project was delivered with no safety incidents, ahead of time and within budget. Three additional wells have also been drilled by Tulip into the same field, the second well was brought on stream on March 24, the third on June 19 and the fourth well will be put into production in the coming days.

Together, the three wells currently on stream are flowing gas from the Q10-A platform at a current combined rate of approx. 3.1 million standard cubic meters per day equivalent to approx. 20,000 barrels of oil equivalent (boe) per day. There have been intermittent production shut-ins due to commissioning, drilling operations and infrastructure maintenance and so far 145 million standard cubic meters of sales gas equivalent to approx. 920,000 barrels of oil have been produced from the field.

The field development plan is based on 5 wells, with an option for a 6th well from the Q10-A platform that has a total facility capacity estimated to be approx. 5 million standard cubic meters per day.

The commissioning of the Q10-A platform and pipeline is complete with only minor items remaining to be completed later in the year.

Tulip Oil Germany Update
Tulip Oil Holding ('TOH'), is also the holder of a 90% holding in Rhein Petroleum ('RP'). In recent months RP has drilled and is currently testing the Steig-1 onshore well in southern Germany. This has delivered a significant oil discovery, the size and value of this are being further evaluated and planning for the development of this oil field has commenced.

Background
TOH is a privately-held exploration and production operator based in The Hague. The Company operates assets in both the Netherlands and in Germany and is owned by funds advised by GNRI, management and staff. TONO owns a 60% interest in the Q07a/Q10 block and is the operator. Energie Beheer Nederland (EBN) holds a 40% interest.

The Q10-A gas field was discovered in 2015 and lies 20km offshore the Netherlands in a shallow 21m water environment. The Q10-A development comprises an unmanned platform with six well-slots. Gas is produced through a 42km pipeline to the P15-D platform from which it is transported to shore.

TOH owns a 90% interest in Rhein Petroleum GmbH which in turn owns and operates a 100% interest in the Graben-Neudorf licence of the Steig-1 well.

Production News in Netherlands Antilles >>

Related Categories: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  Food Supplies  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Unskilled Labors  Utility Systems  Waste Disposal  Water Supply Services  Welding Products/Services 

Related Articles: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Utility Systems  Water Supply Services  Welding Products/Services 


Netherlands Antilles Oil & Gas 1 >> 

More News

Related Links

Gulf Oil and Gas
Copyright 2019 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.