LUKOIL completed construction of the first well as part of Phase 3 of the development of the V. Filanovsky field in the Caspian Sea. The well was drilled with a floating jack up rig Neptune, mounted on a riser block platform.

The newly constructed well has two bores and features TAML level 5 intelligent completion system. The drill depth of the main bore is 3 235 meters. The bottom of the side track is 3 261 meters deep. Planned daily flow rate of oil is 1 838 metric tons.

Produced oil is delivered to the Phase 1 central processing platform via a subsea pipeline. Phase 3, intended to maintain annual oil production at the planned production level of six million metric tons of oil, will integrate western part of the V. Filanovsky field in the development. Operation of the riser block platform is almost automatic and requires minimum involvement of the personnel.

Continuing operational drilling at Phase 1, the company has sidetracked two existing wells.

Development News in Russia >>

Congo >>  8/10/2020 - Zenith Energy Ltd. has incorporated Zenith Energy Congo SA (“Zenith Congo”), a fully owned subsidiary of the Company, created under the laws of the Re...
Iran >>  8/8/2020 - The third generation of sucker-rod pump (SRP) was installed for the first time in ??West Karoun oil fields at well No. 14 of North Yaran field and inc...

Australia >>  8/4/2020 - The National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) has accepted an Offshore Project Proposal (OPP) from Shell Aus...
Australia >>  8/4/2020 - The National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) has accepted an Offshore Project Proposal (OPP) from Shell Aus...

Vietnam >>  8/4/2020 - Pharos Energy plc, an independent oil and gas exploration and production company, has announced that the Joint Operating Company's (JOC) request for a...
Canada >>  8/3/2020 - Calima Energy Ltd’s core assets are the Calima lands that lie within the liquids-rich gas sweet-spot of the Montney Formation in British Columbia, Can...

Related Categories: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  Food Supplies  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Unskilled Labors  Utility Systems  Waste Disposal  Water Supply Services  Welding Products/Services 

Related Articles: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Utility Systems  Water Supply Services  Welding Products/Services 


Russia Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 |

Oil & Gas Projects in Russia >>

More News

Related Links

Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.