Gulf Oil and Gas accountACCOUNT

Last Two Decks Loaded out Simultaneously at SADRA

Source: www.gulfoilandgas.com 2/10/2020, Location: Asia

The two decks, each weighing about 2500 tons, have made 98 percent progress which were simultaneously loaded on the carrier vessel called FLB124 at manufacturing yard of Iran marine industrial company with the method of Push Pull, director of phase 13, Payyam Motamed, was quoted by public relations as saying.

He described the operation as one of the most important steps taken to complete the second chain of offshore facility. Following seafastening and offloading works on the carrier vessel, they will be carried to their locations if the weather is favorable. They are then lifted and placed on their jacket by crane vessel HL5000.

According to Motamed, each deck contains 67000 meters of electrical cabling as well as 36000 dia-inch of piping fabrication and has the capacity to extract 500 million cubic feet of sour gas per day.

Phase13 has been designed to produce 56 million cubic meters of rich gas, 75000 barrels of gas condensate, 400 tons of sulfur a day in addition to 1,100,000 tons of liquid gas, and 1 million tons of ethane a year.

Offshore Platforms News in Iran >>

Norway >>  7/14/2020 - Wintershall Dea has opted to extend the frame agreement with Head Energy concerning modifications at the Brage platform. Head Energy was awarded the f...
New Zealand >>  7/9/2020 - On 7th July, in Vietnam, Damen Song Cam Shipyard, together with joint venture partner Song Cam Shipyard hosted a keel-laying ceremony for the electric...

Brazil >>  7/7/2020 - Petrobras has informed that, after approval by the National Agency for Petroleum, Natural Gas and Biofuels (ANP), the Brazilian Institute for the Envi...
Norway >>  7/6/2020 - Equinor has, on behalf of the licence partners, awarded Apply a framework agreement for engineering and installation services on the North Sea Statfjo...

United Kingdom >>  7/2/2020 - Engineering X – an international collaboration founded by the Royal Academy of Engineering and Lloyd’s Register Foundation – has awarded nearly £1 mil...
Norway >>  6/30/2020 - Kvaerner has been awarded by Allseas a contract to dismantle and recycle three large topsides, three jackets and four bridges from the Valhall and Hod...

Related Categories: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 

Related Articles: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 


Iran Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |

Oil & Gas Projects in Iran >>

More News

Related Links

Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.