Gulf Oil and Gas accountACCOUNT

Last Two Decks Loaded out Simultaneously at SADRA

Source: www.gulfoilandgas.com 2/10/2020, Location: Asia

The two decks, each weighing about 2500 tons, have made 98 percent progress which were simultaneously loaded on the carrier vessel called FLB124 at manufacturing yard of Iran marine industrial company with the method of Push Pull, director of phase 13, Payyam Motamed, was quoted by public relations as saying.

He described the operation as one of the most important steps taken to complete the second chain of offshore facility. Following seafastening and offloading works on the carrier vessel, they will be carried to their locations if the weather is favorable. They are then lifted and placed on their jacket by crane vessel HL5000.

According to Motamed, each deck contains 67000 meters of electrical cabling as well as 36000 dia-inch of piping fabrication and has the capacity to extract 500 million cubic feet of sour gas per day.

Phase13 has been designed to produce 56 million cubic meters of rich gas, 75000 barrels of gas condensate, 400 tons of sulfur a day in addition to 1,100,000 tons of liquid gas, and 1 million tons of ethane a year.

Offshore Platforms News in Iran >>

Norway >>  3/24/2020 - Wintershall Dea has awarded Head Energy a contract for two well hook-ups at the Brage Platform. The engineering phase will start immediately. This is ...
United Kingdom >>  3/18/2020 - Unity, Europe’s largest provider of well integrity technology, services and engineering solutions, has been awarded a three-year contract by Spirit En...

Iran >>  3/7/2020 - The fourth or the last deck belonging to phase 13 called 13C, while observing all safety requirements, was lifted and installed on its jacket by the i...
Japan >>  3/3/2020 - PaxOcean Group has signed a significant newbuilding contract with Penta-Ocean Construction Co., Ltd., to construct a self-elevating platform (SEP) on ...

Related Categories: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 

Related Articles: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 


Iran Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |

Oil & Gas Projects in Iran >>

More News

Related Links

Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.