Gulf Oil and Gas accountACCOUNT

Harvest Midstream Completes the New Ingleside Pipeline

Source: www.gulfoilandgas.com 6/23/2020, Location: North America

Harvest Midstream Company announced the completion of the new Ingleside Pipeline and provided an update on the Harvest Midway Terminal’s construction schedule.

“As a result of the successful and timely completion of the Ingleside Pipeline, Harvest customers will receive direct access to all three Ingleside terminals. This is one of the fastest growing export centers on the Gulf Coast and we are excited to share this growth with our customers,” said Sean Kolassa, President of Harvest Midstream Company.

The Ingleside Pipeline, a 24-mile, 24-inch oil pipeline, has a capacity of 600,000 barrels per day (bpd) with up to 380,000 bpd supplied by the existing Harvest Eagle Ford pipeline systems. The pipeline is currently able to transport volumes to the Flint Hills Resources Ingleside Terminal, and will be capable of shipping barrels to the South Texas Gateway Terminal in July 2020 and the Moda Ingleside Energy Center in September 2020.

“Harvest has always provided our customers with reliable and safe transportation,” said Jason Rebrook, CEO of Harvest Midstream Company. “We look forward to providing that same consistent service with our expanded operations and the additional storage and connectivity in the Ingleside and Corpus Christi markets.”

The pipeline originates at the Harvest Midway Terminal located in Taft, Texas. The terminal covers 160 acres and has the potential to construct up to 10 million barrels of crude storage. Phase 1 construction of the Harvest Midway Terminal is expected to be completed by the end of Q3 2020 and will add new infrastructure capable of pumping the Ingleside Pipeline at 600,000 barrels per day.

Oil and Gas Pipeline >>

Oil and Gas Pipeline News in United States >>

United States >>  7/29/2020 - DTE Midstream, a non-utility business of DTE Energy, announced that test gas is now flowing through its Louisiana Energy Access Project (LEAP) gatheri...
Iran >>  7/26/2020 - Director of phase 13 announced that the pre-commissioning and commissioning operations of infield pipeline connecting platform 13C to 13A was complete...

Malaysia >>  7/21/2020 - Cortez Subsea in partnership with Alam Maritim (M) Sdn Bhd, has announced the successful completion of the first ever subsea pipeline using the Zap-Lo...
United States >>  7/17/2020 - Williams received approval from the Federal Energy Regulatory Commission to move forward with its Leidy South Project that will create 582,400 Dth/d o...

Canada >>  7/7/2020 - Rangeland Midstream Canada, Ltd., a wholly owned subsidiary of Rangeland Energy III LLC, announced that its Marten Hills Pipeline System is in service...
United States >>  7/7/2020 - Crestwood Equity Partners LP provided an update on its Bakken operations including the Arrow gathering system, Bear Den processing plants and the COLT...




United States Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 | 55 | 56 | 57 | 58 | 59 | 60 | 61 | 62 | 63 | 64 | 65 | 66 | 67 | 68 | 69 | 70 | 71 | 72 | 73 | 74 | 75 | 76 | 77 | 78 | 79 |

More News

Related Links

Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.