Orsted's First Dutch Offshore Wind Farm Fully Commissioned

Source: www.gulfoilandgas.com 11/27/2020, Location: Europe

Orsted has fully commissioned the Borssele 1 & 2 offshore wind farm. The wind farm has a capacity of 752 MW, making it the largest offshore wind farm in the Netherlands and the second largest operating offshore wind farm in the world. Borssele 1 & 2 provides enough green electricity to power one million Dutch households. Borssele 1 & 2 is Orsted's first offshore wind farm in the Netherlands.

Henrik Poulsen, CEO and President of Orsted, says:

"This is an important milestone for the green transformation and for Orsted. We're proud that we've commissioned our first offshore wind farm in the Netherlands, who is among the global frontrunners in the energy transition. With Borssele 1 & 2 as the first step, we wish to make a significant contribution to the Dutch transition from fossil to renewable energy. We're proud that we completed this large-scale clean energy project on time and within budget during the COVID-19 pandemic, while maintaining our focus on health and safety."

In 1991 Orsted built the world's first offshore wind farm in Denmark. Since then, Orsted has constructed and is operating more than 25 offshore windfarms across Europe, Asia Pacific and North America. Turbine number 25 installed at Borssele 1 & 2 turbine was at the same time the 1,500th offshore wind turbine installed across Orsted's portfolio.

Steven Engels, General Manager Benelux at Orsted, says:

"It's great that we now can deliver enough green electricity to power one million Dutch households. Orsted has delivered what it promised back in 2016, when we won the tender with a ground-breaking bid price. Realising the first project of the large-scale offshore wind roll out programme in the Netherlands is an important milestone for the Dutch energy transition. I'd like to thank the Dutch national and regional governments and so many other stakeholders who have helped us achieve this result. Zeeland has welcomed us with open arms, which provides an excellent starting point for our operations out of Vlissingen for many years to come. Moreover, it's a good basis for future projects around industry decarbonization in the region, such as the renewable hydrogen project that we announced with Yara."

Flemming Thomsen, Ørsted's Senior Programme Director for Borssele 1 & 2 says:

"Together with our suppliers, our construction team has successfully installed this wind farm at high quality in less than nine months. By introducing additional health and safety measures offshore as well as onshore, we were able to continue construction during a global pandemic. We're grateful and proud of the result delivered and pleased to witness the commissioning of Borssele 1 & 2."

Facts about Borssele 1 & 2
Owner: Orsted
Total capacity: 752 MW
Wind turbines: Siemens Gamesa 8 MW
Size of the site: 112 km2
Number of turbines: 94
Foundation: monopiles
Offshore and onshore grid: TSO TenneT
Operational: Q4 2020
Water depth: 14-36m
Distance to coast: 23 km off the coast of Zeeland
Operation and maintenance base: Vlissingen
Capatity: Can power 1 million Dutch households
Main suppliers: Siemens Gamesa, Sif, Bladt, EEW SPC, EEW OSB, and Nexans
Installation: DEME Offshore, Van Oord



Australia >>  12/12/2024 - The Albanese Government has today declared the Bass Strait offshore wind zone in northern Tasmania, creating new investment, jobs and cleaner, cheaper...
Australia >>  12/12/2024 - The Australian Government declared an area off of northern Tasmania’s Bass Strait as suitable for offshore wind development on 12 December 2024.


Brazil >>  12/12/2024 - Brazil’s Federal Senate has passed the country’s offshore wind bill, passing the legislation on to the President for final approval.

The b...

Canada >>  12/12/2024 - The Canada Infrastructure Bank (CIB) has reached financial close on a $45.8 million loan to support the development of a 34-megawatt wind farm in Hant...

Germany >>  12/12/2024 - RWE awarded tenders for wind farms with total capacity of around 40 MW
Construction on projects in Germany’s northeast and west to begin in 2025<...

Germany >>  12/12/2024 - Kansai, the second-largest electric company in Japan and one of the largest in Asia, will have a minority stake of 49% in the asset, which is currentl...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.