Equinor – Johan Sverdrup Phase 2 – Design Engineering & Follow-up

Source: www.gulfoilandgas.com 1/7/2021, Location: Europe

The Petroleum Safety Authority Norway (PSA) has carried out an audit of Equinor’s management of design engineering and follow-up of barriers for the Johan Sverdrup processing platform (P2) and modification of the riser platform (RP).

Objective
The objective of the audit was to verify Equinor’s management and follow-up for ensuring that design solutions are safe and robust and comply with the preconditions in the PDO (plan for development and operation) and the regulations. This also included experience transfer in the Johan Sverdrup project from phase 1 to phase 2 and it was carried out as a cross-disciplinary project audit.

Result
No regulatory non-conformities were identified.

Three improvement points were identified, relating to:
Barrier management – operational barriers
Materials handling plan
Scaffolding as a temporary attachment point for a lifting device

What happens next?
We have asked Equinor for their assessment of the observations we have categorised as improvement points. The reply deadline is set at 1 February 2021.

Maintenance and Repair News in Norway >>

Scotland >>  3/2/2021 - Global Offshore, a leading provider of cable installation, repair and trenching services to the offshore renewables, utilities and oil & gas markets, ...
Netherlands/Holland >>  2/22/2021 - Van Oord has been awarded a 4-year Operations & Maintenance (O&M) contract by Vattenfall. Working through its MPI Offshore organisation, Van Oord will...

Norway >>  2/18/2021 - The Petroleum Safety Authority Norway (PSA) has carried out an audit of COSL Drilling Europe AS (COSL) and their management of logistics, work at heig...
Saudi Arabia >>  2/18/2021 - The technology group Wärtsilä has signed a 5-year Operation and Maintenance (O&M) agreement with the Saudi Arabian cement producer Umm AlQura Cement C...

Norway >>  2/15/2021 - Var Energi, Equinor, Gassco and Aker BP have received consent to perform manned underwater operations (MUO) in 2021.

Equinor has signed fr...

Norway >>  2/11/2021 - The technology group Wartsila has signed a Wartsila Optimized Maintenance Agreement covering two offshore Well Intervention Vessels owned by Norway ba...




Norway Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 |

More News

Related Links

Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.