BW Energy Provides Q4 2020 Trading Update

Source: www.gulfoilandgas.com 1/18/2021, Location: Africa

BW Energy provides an update on the operation and development of the Dussafu Marin license in Gabon. The Company will publish its financial report for the fourth quarter and full year 2020 on Friday, 19 February 2021.

Gross production from the Tortue field averaged approximately 13,500 barrels of oil per day in the fourth quarter of 2020, amounting to a total gross production of 1.24 million barrels of oil for the period. BW Adolo had scheduled downtime of 11 days in October for its annual maintenance program and to comply with Gabonese production allocations to meet the nation’s OPEC quotas.

BW Energy completed two liftings in the quarter, realising an average price of approximately USD 46.5 per barrel. The latter lifting will be paid to the Company in January 2021. Production cost (excluding royalties) was USD 22.7 per barrel. This includes approximately USD 2.2 million of additional costs related to handling the COVID-19 pandemic in the quarter.

BW Energy’s share of gross production was approximately 914,000 barrels of oil. Net sold volume, which is the basis for revenue recognition in the financial statement, was 1.26 million barrels including approximately 162.000 barrels of fourth quarter DMO deliveries and an over-lift position of around 41,000 barrels at the end of the period.

Execution of Dussafu development plan is progressing with the recent award of a drilling contract for one development well (DTM-7H) and one exploration well. Additionally, BW Energy holds an option for another exploration well subject to the results of the drilling campaign.

In November 2020, BW Energy concluded on an alternative development plan for the Hibiscus/Ruche satellite field, utilising a converted jack-up as an offshore installation. Planning for the Hibiscus Alpha conversion project is progressing with focus on structural engineering and yard selection. The use of a converted jack-up is expected to reduce capital investments by around USD 100 million compared to constructing and installing a new wellhead platform.

BW Energy had a cash balance of USD 120 million at 31 December 2020, compared to USD 145 million at 30 September 2020. The decrease is mainly due to the abovementioned working capital impact of the December lifting and previously announced payments for the acquisition of two jack-ups.

Production News in Gabon >>

Canada >>  3/3/2021 - - Annual sales volumes averaged 68,340 Boe/d (39% liquids) in 2020. Fourth quarter 2020 sales volumes averaged 73,460 Boe/d (42% liquids), ahead of gu...
Colombia >>  3/3/2021 - Parex Resources Inc. is a company headquartered in Calgary, Alberta that focuses on sustainable, profitable, conventional oil and gas production. The ...

Brazil >>  3/2/2021 - Alvopetro Energy Ltd. announces record daily average February sales volumes, updated results from our 183-1 deep basin Gomo natural gas well, and the ...
Colombia >>  3/2/2021 - Canacol Energy Ltd. is pleased to provide the following information concerning its February 2021 natural gas sales and drilling program. ...

United Kingdom >>  3/2/2021 - EnQuest has begun cessation of production activities on the Northern Producer floating production facility (FPF) at the Don fields in the North Sea.
Algeria >>  2/26/2021 - Neptune Energy announced operational and financial guidance for 2021, ahead of its full year 2020 results on 11 March. ...




Gabon Oil & Gas 1 >>  2 | 3 | 4 |

Oil & Gas Projects in Gabon >>

More News

Related Links

Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.