88 Energy Provides Operations Update

Source: www.gulfoilandgas.com 3/2/2021, Location: North America

88 Energy has provided an update related to its operations in the NPR-A region of the North Slope of Alaska.

Highlights

- Rig mobilisation progressing well

- Spud now scheduled for 8th March 2021

Details

88 Energy reports that the mobilisation of Rig 111 to the Merlin-1 location is progressing well, with only minor delays due to weather. The spud date is now scheduled for 8th March.

The Merlin-1 well will initially be drilled to 1,500', then surface casing will be installed and the Blow Out Preventer system tested. This is expected take approx. one week to execute.

The well will then be deepened through the target horizons in the Nanushuk Formation to a maximum total depth of 6,000'. Logging while drilling and mudlogging will provide initial indications as to the prospectivity of the well during this part of the operation, which is expected take three to five days. A sophisticated wireline logging suite will then be run, including sidewall cores and downhole sampling. Wireline logging is expected to take five to seven days.

If the results from the wireline logging are encouraging, then the well will be completed with casing and a flow test conducted.

The drilling of the second well in the program, Harrier-1, remains subject to permitting, Merlin-1 results and weather / schedule.

Managing Director, Dave Wall, commented:

'Pre-spud operations are now entering the final phase as Rig 111 makes it way to the drilling location for Merlin-1. Success at Merlin-1 could yield over 300 million barrels net to 88E and open up further prospectivity at Project Peregrine, in addition to unlocking the substantial proven resource at the adjacent Umiat oil field, which is 100% owned by 88 Energy.

Metrics for discovered oil were demonstrated by the late 2017 Oil Search transaction where US$3.10 per barrel was paid, in a low oil price environment, for an interest in the Pikka Field, which is a discovery in the Nanushuk Formation. Success at Merlin-1 would be transformational for our shareholders and we look forward to providing further information on operations over the next 4 to 6 weeks.'

About Project Peregrine - Imminent Drilling

Project Peregrine is located in the NPR-A region of the North Slope of Alaska and encompasses ~195,000 contiguous acres. It is situated on trend to recent discoveries in a newly successful play type in topset sands in the Nanushuk formation. 88 Energy has a 100% working interest in the project that will reduce to 50% post the completion of funding as part of a recent farm-in, whereby 88E is carried on the first US$10m (of an estimated US$12.6m total cost) for the Merlin-1 well.

The Merlin-1 well is scheduled for spud in early March 2021 and is targeting 645 million barrels of gross mean prospective resource. Flow testing of Merlin-1 is planned if wireline logging confirms a discovery. A second well, Harrier-1, is intended to commence immediately following completion of operations at Merlin-1, subject to results from Merlin-1, schedule and permit approvals. Harrier-1 is targeting gross mean prospective resource of 417 million barrels and is expected to cost ~US$7m.

Each of the Merlin and Harrier prospects is located on trend to an existing discovery (see next figure), in the same play type (Nanushuk topsets). This has de-risked the prospects considerably and resulted in a relatively high independently estimated geologic chance of success.


Gabon >>  4/19/2021 - BW Energy Limited is pleased to announce the re-start of a three-well drilling campaign on the Dussafu license offshore Gabon consisting of two explor...
Germany >>  4/19/2021 - Neptune Energy has announced drilling has begun at its operated Adorf Z16 gas development well in the municipality of Hoogstede, north western Germany...

Australia >>  4/14/2021 - Buru Energy Limited is pleased to advise confirmation of the drilling rig for the 2021 Canning Basin program, and substantial progress on pre-spud act...
Argentina >>  4/12/2021 - President Energy, the energy company with a diverse portfolio of production and exploration assets focused primarily in South America, has provided an...

Australia >>  4/12/2021 - Central Petroleum Limited (CTP) (“Central”) advises that Range-6, the first well in the three well Range Pilot Programme, spudded on 11th April 2021 a...