Union Jack Oil, a UK focused onshore hydrocarbon production, development and exploration company, has provided an update in respect of the future planned test programmes at West Newton.

The Company holds a 16.665% economic interest in PEDL183, encompassing an area of 176,000 acres and located within the Western sector of the Southern Permian Basin, onshore UK, North of the river Humber. PEDL183 contains the WNA-1, WNA-2 and WNB-1Z discoveries.

Highlights:

- Draft Environmental Agency permit received for completion, well clean-up and Extended Well Test ('EWT') at WNB-1Z and additional wells at the West Newton B site

- First phase of evaluation, including Cased Hole Logging Programme and Vertical Seismic Profiling, of WNB-1Z to commence in April 2021

- Processing and interpretation of data expected to take two weeks and will inform completion, well clean-up and EWT operations for WNB-1Z well

- Preparations for updated Competent Person's Report at West Newton in progress

Environmental Agency Permit

The Operator of PEDL183, Rathlin Energy (UK) applied to vary the West Newton B Wellsite permit and has received a draft of the varied permit from the Environmental Agency ('EA') that will accommodate completion, well clean-up and EWT operations. This permit includes the WNB-1Z discovery well and any additional wells planned for the West Newton B site.

An EA permit is already in place at the West Newton A site, that includes further clean-up and EWT operations on the WNA-2 well.

Cased Hole Logging Programme ('CHLP') and Vertical Seismic Profiling ('VSP') Survey

The first phase of the evaluation programme on the WNB-1Z discovery well is planned to commence in April 2021 and will initially be comprised of a customised CHLP including a cement bond log, a Weatherford Raptor evaluation tool to log the Kirkham Abbey formation and a VSP.

The Raptor tool is a pulsed neutron wireline logging device that provides a quantification and advanced analysis of oil, gas and water saturations and potential fluid contacts in a cased wellbore.

This cased hole logging activity will be followed by a VSP survey that will provide a high-resolution calibration of the existing 3D seismic data and is considered to be a more accurate method of calibrating previously interpreted formation tops and previously calculated time-estimated formation depths.

Following completion of the CHLP and VSP survey, the processing and interpretation of the data acquired is expected to take approximately two weeks and will help inform the completion, well clean-up and EWT operations on the Kirkham Abbey formation for the WNB-1Z well.

Competent Person's Report

Data gathered from the completion and EWT programme will be incorporated with the existing information to produce a new Competent Person's Report ('CPR').

Discussions regarding the appointment of a highly respected global consultancy to produce a CPR on West Newton are at an advanced stage. The JV expects to be in a position to announce this appointment in the near future.


Egypt >>  5/4/2021 - United Oil & Gas PLC ("UOG") is pleased to provide the following update on the testing of the ASD-1X exploration well in the Abu Sennan concession, on...
Argentina >>  4/30/2021 - President Energy (PPC), the energy company with a diverse portfolio of production and exploration assets focused primarily in South America, provides ...

China >>  4/27/2021 - The North China Oil and Gas Branch deployed the JPH-489 well in the Dongsheng Gas Field in the northern Ordos Basin. One of a batch of high-yield well...
United Kingdom >>  4/20/2021 - Union Jack Oil plc, a UK focused onshore hydrocarbon production, development and exploration company, is pleased to announce an operations update and ...

Argentina >>  4/19/2021 - Interoil Exploration and Production ASA (Interoil) is pleased to confirm that after successful inspection and testing, the workover rig has now arrive...
Australia >>  4/19/2021 - Strike Energy has provided an update on the West Erregulla 4 well on behalf of the EP469 Joint Venture.

Current Operations

...





Gulf Oil and Gas
Copyright 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.