Offshore Part of One Line of Nord Stream 2 Has Been Mechanically Completed

Source: www.gulfoilandgas.com 6/10/2021, Location: Asia

The offshore part of one line of Nord Stream 2 has been mechanically completed. Pipelay was completed on June 4, 2021, and the above water tie-in was performed – the offshore pipeline sections laid from Russia and Germany have thus been interconnected.

Starting from tomorrow, the required pre-commissioning activities will be carried out to prepare for gas-in.

Offshore pipelay works on the second line are ongoing. All activities are in accordance with the respective permits.