Gas Filling of the First Nord Stream 2 String Started

Source: www.gulfoilandgas.com 10/4/2021, Location: Asia

The gas-in procedure for the first string of the Nord Stream 2 pipeline has started. This string will be gradually filled to build the required inventory and pressure as a prerequisite for the later technical tests.

Previously, the first string of the pipeline underwent pre-commissioning activities to assure the pipeline integrity.

This included the internal inspection by special devices (pipeline inspection gauges), as well as external visual and instrumental surveys of the pipeline. Nord Stream 2 will inform about further technical steps in due time.

The pipeline is built and independently certified according to applicable technical and industry standards to ensure reliable and safe operations. Pre-commissioning steps for the second string are ongoing.


Canada >>  11/26/2021 - Enbridge Inc. received a decision from the Canada Energy Regulator (CER) on the Company's commercial proposal to offer transportation contracting on i...
United States >>  11/18/2021 - Magellan Midstream Partners, L.P. has launched an open season to assess firm customer interest in the potential expansion of the partnership's refined...

Brazil >>  11/16/2021 - Petrobras and Potiguar E&P, a subsidiary of PetroReconcavo, signed, contracts for the flow of natural gas produced on land by Potiguar E&P in the stat...
Germany >>  11/16/2021 - The Federal Network Agency has temporarily suspended the process for the certification of Nord Stream 2 AG as an independent transport network operato...




Gulf Oil and Gas
Copyright 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.