Last Gas Compressor of Phases 22-24 Online

Source: www.gulfoilandgas.com 12/11/2021, Location: Asia

Asaluyeh (POGC) – The operator of the development project of phases 22 to 24 of South Pars Gas Field said the last gas turbo-compressor of the phases' refinery has been successfully commissioned.

Ali Asghar Sadeghi stated: “In order to obtain the necessary preparation for the stable supply of fuel in winter, the last turbo-compressor of the refinery of phases 22 to 24 was put into operation.”

He said that the gas transmission unit of the refinery of phases 22 to 24 includes 6 turbo-compressors for sending methane to the national trunkline.

The operator of phases 22 to 24 of South Pars announced that gas production capacity of the project would be 56 million cubic meters per day, and said: “With the entry of gas into the refining and gas processing lines, in addition to producing hydrocarbon products such as gas condensate, liquefied gas, ethane and sulfur, a daily capacity of 50 million cubic meters of sweet gas will be sent through the 42-inch pipeline to the national gas transmission network.”


China >>  7/28/2022 - INEOS and SINOPEC have today signed three back-to-back deals worth a combined value of $7bn. These landmark agreements are expected to generate a comb...
Azerbaijan >>  7/18/2022 - Ursula von der Leyen, president of the Commission, and Kadri Simson, commissioner for energy, met with Ilham Aliyev, president, and Parviz Shahbazov, ...

China >>  7/18/2022 - According to the relevant provisions of the Regulations of the People's Republic of China on the Exploitation of Offshore Petroleum Resources in Coope...




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.