Order to KCA Deutag – Askepott – Maintenance Management

Source: www.gulfoilandgas.com 12/22/2021, Location: Europe

The Petroleum Safety Authority Norway (PSA) has issued KCA Deutag with an order following the identification of serious breaches of the regulations in an audit of KCA Deutag’s management of maintenance. Notification of the order was made on 2 December 2021 and the order was issued on 20 December 2021. The audit itself was conducted from 23 September to 1 October 2021.

Objective
The objective of the audit was to monitor KCA Deutag’s management of maintenance on board the Askepott facility.

Result
Five non-conformities were identified, concerning:
Classification
Maintenance programme
Planning and prioritisation
Maintenance efficiency
Barriers

Order
On the basis of our observations in the audit, we have now issued KCA Deutag with the following order:

Pursuant to the Framework Regulations, section 69 concerning administrative decisions, the Activities Regulations, section 46 concerning classification and the Activities Regulations, section 48 concerning prioritisation, KCA Deutag is ordered to implement the following measures:

Review the classification of systems and equipment and establish criteria for prioritising, with associated deadlines, the execution of the individual maintenance activities for the Askepott facility, with reference to Chapter 5 of the audit report. Non-conformity

5.1.1 concerning classification
Non-conformity 5.1.3 concerning planning and prioritisation
The work is to include an analysis of why key elements in the basis for managing maintenance on Askepott have not been rectified.

Implement measures to ensure that actions and lessons learned as a result of the above items in the order are also applied to all facilities with AoCs for which KCA Deutag is responsible in Norway.

The deadline for complying with part 1 of the order is 3 October 2022.

We request KCA Deutag to arrange a status meeting in mid-Q1 2022. For part 2 of the order, we request a time-delimited schedule for the work.

We are also to be notified when the order has been complied with.


Norway >>  5/16/2022 - The extensive repairs at Melkøya have been completed, but the run-up of the plant takes somewhat longer than planned. ...
Brazil >>  5/4/2022 - Prosafe has been awarded a contract by Petróleo Brasileiro SA (‘Petrobras’) for the provision of the Safe Notos semi-submersible vessel for safety and...

Lithuania >>  4/26/2022 - Operations of Klaipeda liquefied natural gas (LNG) terminal will be temporarily suspended from 07:00 on 27 April to 07:00 on 30 April due to the sched...
Egypt >>  4/25/2022 - The technology group Wärtsilä’s strong relationship with one of Egypt’s major independent power producers (IPPs) is further enhanced with a new order....




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.