Equinor – Snorre A – Barrier Management

Source: www.gulfoilandgas.com 1/28/2022, Location: Europe

The Petroleum Safety Authority Norway (PSA) has carried out an audit of Equinor and their management of barriers at Snorre A.

The audit was conducted between 4 and 8 October 2021 and must be seen in the context of the audit of the onshore organisation carried out in 2020.

Objective
The objective of the audit was to ensure that Equinor's management of technical barriers at Snorre A, particularly within technical safety, process safety and risk management, complies with the authorities' requirements.

Result
Five non-conformities were identified during the audit. These concerned:
- Passive fire protection
- Operational barriers
- Event notification procedure
- Factors with a potential to affect explosion risk
- Non-conformity handling

Three improvement points were also identified. These concerned:
- Open drainage
- Maintenance system
- Documentation

What happens now?
We have asked Equinor to report on how the non-conformities will be addressed. We have also requested the company's assessment of the improvement points observed. The reply deadline is set at 1 March 2022.


Norway >>  8/11/2022 - Aker Solutions has been awarded a sizeable [1] contract from Aker BP to provide the subsea production system for the Trell & Trine field development, ...
Norway >>  8/11/2022 - Subsea 7 announced the award of a sizeable1 contract by Aker BP for the Trell & Trine field development, located in the Alvheim area of the North Sea....

United Kingdom >>  8/2/2022 - Aker Solutions has been awarded a contract(1) from Shell UK for the delivery of a not permanently attended installation (NPAI) for the Jackdaw gas fie...
Netherlands/Holland >>  7/21/2022 - As part of the current Partnership Agreement between Technip Energies and Neste, Technip Energies (TE) has been awarded a large contract by Neste for ...




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.