Trading Update for Seaway 7 ASA

Source: www.gulfoilandgas.com 6/13/2022, Location: Europe

Seaway 7 ASA (the “Company”) (Euronext Growth: SEAW7) announced updates on its projects and updated Adjusted EBITDA guidance for full year 2022.

As a result, the Company has updated its guidance for full year 2022. Revenue is expected to be in line with previous guidance towards $1 billion with an Adjusted EBITDA margin now expected to be approximately 6%.

The Company has encountered reduced progress on the Hollandse Kust Zuid project relating primarily to adverse weather conditions and mechanical breakdowns. The cost increases associated with these challenges will result in a contract loss provision of approximately $30 million to be recognised in the second quarter 2022.

The installation of foundations for the Dogger Bank A and B project is expected to commence in 2022, as originally planned, although due to Seaway Alfa Lift’s delivery delay, Seaway Strashnov will now be deployed on the project for a full 2023 campaign. The increased cost of the extended Seaway Strashnov campaign will result in an increase in the contract loss provision of approximately $35 million. This loss will be reflected in a revision to the preliminary purchase price adjustment relating to the combination to form Seaway 7 ASA and will not affect Adjusted EBITDA. This revision will be recognised in the second quarter 2022.

The Company has also encountered reduced progress on the Formosa 2 project in Taiwan, related primarily to lower offshore productivity. Pursuant to an indemnity from Subsea 7 as part of the combination to form Seaway 7 ASA, the related costs will be reimbursed by Subsea 7 and will not affect Seaway 7.

As regards other operations, Seaway Ventus has commenced construction with the laying of the keel in early June 2022, in accordance with the planned delivery schedule, while Seaway Alfa Lift is now expected to join the fleet in the second half 2023.

The Seagreen project, which is significant to the Company’s portfolio, continues to perform well with 98 of the 114 jackets fabricated and 26 jackets installed. All jackets are scheduled to be installed during 2022, as originally planned, with S7000 Heavy Lift Vessel back in field delivering its scope.


Vietnam >>  12/11/2024 - In a ceremony in Rauma, Finland, Damen Shipyards Group and Kongsberg Maritime have celebrated the delivery of the 1500th Kongsberg azimuth thruster to...
Belgium >>  12/10/2024 - In a significant project that has restored a critical infrastructure element, Sarens successfully completed the transport and installation of the Buda...

United States >>  12/10/2024 - GATE Energy is pleased to announce it has been awarded the commissioning management and execution contract from Shell Offshore, Inc. for the Sparta se...
Japan >>  12/9/2024 - Mitsui O.S.K. Lines, Ltd. (MOL; President & CEO: Takeshi Hashimoto) today announced that on December 7, MOL Group company MOL Cruises, Ltd. (President...

Norway >>  12/8/2024 - We are pleased to inform that we have successfully delivered “IT Infinity” to I.T. International Telecom Marine SRL (IT), after converting the vessel ...
Denmark >>  12/2/2024 - A.P. Moller - Maersk (Maersk) has signed agreements with three yards for a total of 20 container vessels equipped with dual-fuel engines. Combined, th...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.