Arrow Exploration Announces the Results of Rio Cravo Sur-1

Source: www.gulfoilandgas.com 6/27/2022, Location: South America

The Rio Cravo Sur-1 ("RCS-1") well testing findings on the Tapir Block in the Colombian Llanos Basin are now available, and Arrow Exploration Corp. (AXL) ("Arrow") is pleased to share them.

The RCS-1 well was spud on May 23, 2022. RCS-1 targeted a three-way fault bounded structure with multiple high-quality reservoir objectives on the Tapir Block in the Llanos Basin of Colombia. The well was drilled to a total measured depth of 8,656 feet (8,105 feet true vertical depth) and encountered six hydrocarbon bearing intervals totaling 55 net feet of oil pay.

Specific production test rates for the isolated new zones (shallowest to deepest) include:
- Carbonera C7B: tested 1872 bopd (net 936 bopd) peak rate of 30 API crude.
The zone was tested on June 22nd for 33 hours at an average rate of 1076 bopd (net 538 bopd).
- Ubaque: tested 184 bopd (net 92 bopd) peak rate of 12-13 API crude.
The zone was tested June 13th for 38.5 hours at an average rate of 33 bopd (net 16.5 bopd).

Test results are not necessarily indicative of long-term performance or ultimate recovery. After the C7B test performance, the decision was made to put the C7B on production. Arrow decided not to test the up-hole C7 zones, and the Gacheta C, as they had been proven to be oil bearing in RCE-2.

The test of the Gacheta B zone was cut short due to formation water production.

Marshall Abbott, CEO of Arrow commented:
“We’re encouraged by the material results of RCS-1, the third well on the Tapir block. RCS-1 identified new zones for further exploitation with flowing results returning better than expected.”

“We’re currently completing the C7B zone, targeting to be on stream this week. This increases Arrow’s production and reserves. The Company intends to bring RCS-1 on slowly and increase production to best manage the oil reservoir.”

“Arrow’s current production is providing positive cashflow for the Company during a high commodity price environment. Continued strong production rates from existing tied-in wells combined with the encouraging results from new drills in Colombia support the Company’s objective of achieving a production rate of 3,000 boe/d within 18 months of its AIM listing (completed in October 2021). This is an exciting time for Arrow, and we look forward to providing further updates on our progress.”

The RCS-1 well costs came in under budget.


Australia >>  8/15/2022 - HIGHLIGHTS
• All new wells online and pumping.
• Water production in excess of 30,000 BWPD with significant excess capacity remaining shou...

Australia >>  8/15/2022 - Key points:
• The Mahalo North 1 pilot well has achieved a material increase in gas rate over the last three weeks.
• Gas production now ove...


Australia >>  8/15/2022 - Highlights
• The Tanumbirini 2H (T2H) and Tanumbirini 3H (T3H) wells in EP 161 (Santos 75% and operator, Tamboran 25%) are currently flowing at 4...

Australia >>  8/11/2022 - • 2.6 million standard cubic feet (mmscf) per day sustained initial flow rate achieved over the first 91 hours of flow testing with minimal decline in...

United Kingdom >>  8/11/2022 - Hurricane Energy plc, the UK based oil and gas company, provides an update on Lancaster field operations and net free cash balances as of 31 July 2022...
Egypt >>  8/4/2022 - An update on the drilling of the Al Jahraa-14 development well (AJ-14) in the Abu Sennan licence, onshore Egypt, is being released by United Oil & Gas...




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.