Cambay C-77H Re-frac Operations Update

Source: www.gulfoilandgas.com 6/23/2022, Location: Asia

Oilex Limited is pleased to announce the following update with respect to its operations in India.

C-77H Re-frac Operations Update
The workover rig arrived on location at the C-77H wellsite on June 20th 2022 and is being rigged-up in preparation to pulling the completion string from the C-77H wellbore.

Civil works to prepare the wellsite for the re-fraccing operations have been completed. All major services and equipment have been secured for the hydraulic fraccing operation which is scheduled to commence mid-July 2022.

The fraccing operation is anticipated to last 7 days and will be followed by flow-back and testing. We currently expect to be able to announce the results of the re-frac operation in August 2022.


China >>  7/28/2022 - INEOS and SINOPEC have today signed three back-to-back deals worth a combined value of $7bn. These landmark agreements are expected to generate a comb...
Azerbaijan >>  7/18/2022 - Ursula von der Leyen, president of the Commission, and Kadri Simson, commissioner for energy, met with Ilham Aliyev, president, and Parviz Shahbazov, ...

China >>  7/18/2022 - According to the relevant provisions of the Regulations of the People's Republic of China on the Exploitation of Offshore Petroleum Resources in Coope...




Gulf Oil and Gas
Copyright 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.