Jupiter Power Announces Commercial Operations of its 200MW Crossett Facility

Source: www.gulfoilandgas.com 6/28/2022, Location: North America

· New 200MW/200MWh facility in Crane County achieved commercial operations and is one of the largest battery energy storage projects in ERCOT
· Jupiter Power’s total dispatchable energy storage capacity is now over 450MWh, and the company has another 200MWh project in late-stage commissioning and over 500MWh of projects in late stages of development
· Jupiter Power’s ERCOT battery energy storage projects provide fast-responding, firm dispatchable power to enhance reliability and time-shift renewable energy production to times of high consumer demand

Jupiter Power LLC (“Jupiter Power”) announced that Crossett Power Management (“Crossett”), a battery energy storage facility located in Crane County, Texas, has commenced commercial operations.

Crossett, a 200-megawatt (MW) facility with 200-megawatt hours (MWh) of duration, is Jupiter’s second transmission-connected project to begin operations, demonstrating Jupiter’s continued commitment to the ERCOT market and representing a significant investment in Crane County.

Crossett joins Flower Valley II, a 100MW/200MWh transmission connected facility currently operating in Reeves County, Texas, and three distribution connected facilities, positioning Jupiter Power as the largest developer and operator of battery energy storage projects by total duration on the ERCOT grid. Additionally, Jupiter Power is commissioning a subsequent 100MW/200MWh project in West Texas that will be in commercial operations in the summer of 2022.

“We reach yet another significant milestone in our ERCOT battery energy storage portfolio with the commencement of commercial operations at the Crossett facility,” said Mike Geier, Chief Technology Officer, Jupiter Power. “We have witnessed the strain that the Texas climate can put on the grid during unseasonably warm days. Jupiter Power’s projects like Crossett and Flower Valley II are optimally sited where the grid needs support to enhance resiliency both cost-effectively and reliably.”

Jupiter Power’s fleet will improve reliability in ERCOT as Texas approaches peak summer demand. Battery energy storage facilities can “time shift” or store low-cost, off-peak energy and discharge it during periods of high demand. Battery energy storage can provide additional support to electricity grids to manage demand through ancillary services, managing load and congestion and resiliency.


Australia >>  8/4/2022 - Charter Hall Group (Charter Hall or the Group) is pleased to announce it has signed a significant Power Purchase Agreement (PPA) with global renewal e...
Spain >>  8/1/2022 - Prospex Energy PLC, the AIM quoted investment company focused on European gas and power projects, is pleased to provide an update on the production an...

United States >>  8/1/2022 - Duke Energy Carolinas made its annual filing July 29 with the Public Service Commission of South Carolina (PSCSC) for costs associated with the fuel u...
United Arab Emirates >>  7/29/2022 - Dubai Electricity and Water Authority (DEWA) has enhanced integration between different energy resources in its smart grid through its Virtual Power P...

Chile >>  7/28/2022 - - Enel Chile signed an agreement with Sociedad Transmisora Metropolitana and its controlling company Inversiones Grupo Saesa to sell its 99.09% stake ...
France >>  7/28/2022 - - Colin Davidson, High Voltage Direct Current (HVDC) Consulting Engineer at GE Renewable Energy’s Grid Solutions business, awarded the IEEE Power & En...




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.