WELL: West Akcakoca-1
Spudded November 26, 2022. Days since spud: 13
Week Summary:
- Drilled 17 ½” section to planned depth, 1008 measured depth (MD). The well inclination is 60 degrees at section total depth (TD). Well trajectory is very close to the original plan with great success.
- Set 13 3/8” casing, shoe at 1005 m (MD)
- Cemented up to the surface
- Further Activities:
- Wait on cement to harden (WOC)
- Skid Rig over the Guluc-2 slot and start drilling the Guluc-2 well.
Guluc-2 has a similar well program and will start with a 17 ½” section. Therefore, it is anticipated to finish the first section sooner than West Akcakoca-1.