Vulcan Energy Announces December Quarterly Activities Report

Source: www.gulfoilandgas.com 2/2/2023, Location: Europe

Vulcan Energy Resources Limited continued to operate its commercial renewable energy plant successfully and deliver on its strategy to develop the Zero Carbon Lithium™ Project during the December 2022 Quarter (“the Quarter”). Key highlights during the Quarter include Vulcan achieving operational advancements in successfully demonstrating its own in-house lithium extraction sorbent, VULSORB™, and producing the highest grade, lowest impurity lithium hydroxide (LiOH) from its pilot plant, as the Definitive Feasibility Study (DFS) for Phase One approaches its conclusion.

Highlights:

Renewable energy operations
• Produced 6,350 MWh of gross baseload, renewable energy from Vulcan’s operational geothermal wells and plant at Natür3Lich Insheim, at an average selling price of €0.26/kWh, helping Germany to respond to the energy and climate crises.

Phase One integrated Zero Carbon Lithium™ and renewable energy Project development
- Vulcan received approval from the state authority in Rhineland-Pfalz, Germany, for the Operating Plan for Vulcan’s lithium extraction Demonstration Plant (Demo Plant). On-site works are ongoing, and once operational, expected by mid-year, it is intended that the Demo Plant will train Vulcan’s team in a pre-commercial setting prior to commercial plant construction and operation.
- Vulcan’s Pilot Plant successfully produced the data required for Vulcan’s Phase One DFS, after thousands of hours of operation, having successfully operated since April 2021.
- The Phase One DFS is progressing and is on track for finalisation in Q1 2023, after which the project will move into a bridging phase, toward ordering long lead commercial equipment.
- Vulcan successfully developed, tested, and demonstrated its own in-house lithium extraction sorbent, VULSORB™, for sustainable lithium extraction from the Upper Rhine Valley Brine Field and Vulcan’s Zero Carbon Lithium™ Project. Vulcan announced it had produced the highest grade, lowest impurity LiOH from its Pilot Plant, located at its commercially operational geothermal renewable energy plant, at its Zero Carbon Lithium™ Project.
- Vulcan executed two agreements to expand its development footprint around its core, Phase One area.
- 3D seismic works in the Phase One area were completed successfully. A Resource update is expected imminently.
- Vulcan’s transition and focus on project execution capability development for Phase One continued, led by Deputy CEO Cris Moreno, who was appointed during the Quarter. Recruitment continues to gather momentum to this end, with over 200 personnel now in-house.

Phase Two and future project pipeline
•3D seismic survey works commenced on the ground in one of Vulcan’s planned Phase 2 lithium and geothermal energy development areas in the Mannheim district of the Upper Rhine Valley Brine Field. These works followed prior approval of the main operating plan by the state directorate. The results will be used in feasibility studies for Phase 2, which plans to incorporate the Mannheim area.
•Vulcan announced it had started several initiatives to expand its Zero Carbon Lithium™ business into France, specifically Alsace; this is a natural extension of the Upper Rhine Valley GeothermalLithium Brine Field. Vulcan’s previous work on the French side of the border indicated high lithium grades in Alsace brine of 214 mg/L Li and low impurities (inc. Si, Mn, Fe) (see ASX 10 March 2021), suggesting brine composition in Alsace is materially similar as the brine composition across the border at Vulcan’s operations in Germany, meaning Vulcan’s sustainable lithium production process is applicable across the whole field.

Other
Vulcan changed its financial year end from June 30th to December 31st, effective from July 1st, 2022. The change of financial year now aligns with the German financial year, following the Company’s listing on the Frankfurt Stock Exchange (FSE) regulated market in the Prime Standard market segment.

Subsequent to the Quarter:
- Sustainalytics, a Morningstar Company that is a leading independent ESG and corporate governance research, ratings and analytics firm, delivered Vulcan’s first publicly available ESG Risk report in January, giving Vulcan an overall low ESG Risk Score of 16.8, which puts Vulcan in the top 2nd percentile of all chemicals companies, and 1st among peers of equal market capital size, surveyed by Sustainalytics. This demonstrates Vulcan’s industry leading ESG management and performance.
- Vulcan recently signed a Binding Term Sheet with Stellantis for the first phase of a multiphase project aimed at decarbonising the energy mix of the Rüsselsheim auto manufacturing site in the Upper Rhine Valley, Germany, through the development of new geothermal projects.

Vulcan’s Managing Director and CEO, Dr. Francis Wedin commented, “The progress made during the last quarter of 2022 is testament to our rapidly growing team, who are working hard to execute on Phase One of our Zero Carbon Lithium™ Project, which aims to provide domestic lithium production for the auto industry, as well as renewable heating production on a larger scale for Europe, from 2025. We believe the Zero Carbon Lithium™ Project is crucial for Europe, and will help to alleviate the energy crisis, support the decarbonisation of energy and lithium production, and mitigate the lithium supply issues for the of the European auto industry.

“As well as obtaining key approvals for our Demo Plant, we demonstrated our own in-house lithium extraction sorbent, which is an important asset for Vulcan, and produced our highest-grade lithium hydroxide to date from our Pilot Plant, which has just under two years of successful operation. The DFS for Phase One is on track for delivery this Quarter, after which we will enter a bridging phase towards ordering long lead items for our commercial lithium plant.

To this end, we welcomed Cris Moreno as Deputy CEO during the Quarter. Cris comes from a highly successful background of large-scale international project execution and delivery in the energy and lithium battery sector, and is focused on leading the build out of our project execution capability towards our targeted start of commercial lithium production in 2025.”

Vulcan’s Deputy CEO Cris Moreno said, "I'm very excited to have joined the Vulcan team. Our immediate focus is the delivery of Phase One of our Zero Carbon Lithium ™ Project. Aimed to be the world's first, our project is unique, integrating geothermal energy and lithium production innovatively and circularly, ensuring we deliver carbon-neutral, domestically sourced energy, and lithium from Europe, for Europe”.

Safety
Vulcan prioritises the health, safety and wellbeing of the Vulcan team, contractors, and stakeholders. Vulcan is pleased to announce that there were no HSE-relevant safety incidents during the December Quarter. In November Vulcan employed a dedicated HSEQ Manager. Their initial action items were to develop a full contractor training process as well as assist with ISO15001:2015, Occupational Health and Safety certification, to compliment already achieved ISO 14001 and 9001 certifications. Vulcan will continue to remain focused on adding ongoing safety improvements and embedding safety procedures as the Company transitions into the execution phase of the Zero Carbon Lithium™ Project.

Renewable energy operations
Vulcan’s operating geothermal renewable energy plant, Natür3Lich Insheim generated €1.64 million revenue for the Quarter. During the period, the power plant fed approximately 6,350 MWh of renewable electricity into the grid, supplying 7,500 households with power, and avoiding CO2 emissions, helping Germany to respond to the energy and climate crises in Europe.

Phase One integrated Zero Carbon Lithium™ and renewable energy Project development
Vulcan received approval from the state authority in Rhineland-Pfalz, Germany, for the Operating Plan for Vulcan’s lithium extraction Demonstration Plant (Demo Plant). On-site works are ongoing, and once operational, expected by mid-year, it is intended that the Demo Plant will train Vulcan’s team in a precommercial setting and improve operational readiness prior to commercial plant construction and operation, with initial Phase One commercial production targeted for end 2025.

During the Quarter, the team moved into an expanded laboratory, to further deepen their understanding of lithium processing and to optimise the process to inform the Definitive Feasibility Study (DFS). With its state-of-the-art equipment for wet and solid-state analyses, including full in-house inductively coupled plasma optical emission spectrometry (ICP-OES) and Ion chromatography (IC) analytical capability, the new laboratory has enabled Vulcan to expand its core competencies and centralise its proprietary lithium processes and deliver the required information for the Phase One DFS.

A highlight during this period was the successful development of Vulcan’s own in-house lithium extraction sorbent, VULSORB™. The team has successfully demonstrated multi-cycle sorption tests on Upper Rhine Valley geothermal brine using multiple commercially available and in-house aluminatebased sorbents. All sorbents have demonstrated >90% lithium recovery, in line with the assumptions used in the Pre-Feasibility Study. Data from VULSORB™ has been incorporated into the DFS.

In October the Vulcan chemical engineering team successfully produced the highest grade, lowest impurity LiOH to date from its Pilot Plant. The LiOH was produced from Vulcan’s lithium extraction pilot plant, located at Vulcan’s commercial geothermal renewable energy plant in the Upper Rhine Valley Brine Field (URVBF) in Germany, with downstream electrolysis processing offsite, as per Vulcan’s planned commercial Zero Carbon Lithium™ Project. The latest material produced graded 57.1% LiOH, easily exceeding the best-on-the-market battery grade specification of 56.5% LiOH required from offtake customers. Impurities were well below market specification minimums. The lithium chloride extracted by the sorbent in the pilot plant was recovered with water and sent offsite, where it was purified and concentrated by a third-party provider to prepare the lithium chloride for electrolysis to produce lithium hydroxide solution. The solution was then crystalized to produce battery grade lithium hydroxide monohydrate.

The embodied renewable heat within Vulcan’s brine should enable Vulcan to use the commercially proven sorption method of lithium extraction at relatively low cost, which produces a very high purity LiCl product, which in turn enables the use of Li electrolysis to directly produce very high grade, low impurity LiOH. Vulcan’s Pilot Plant has been successfully operating since April 2021 and has now produced sufficient data to complete Vulcan’s Phase 1 Definitive Feasibility Study (DFS), which is scheduled for Q1 ‘23.

The Phase One DFS is progressing and is on track for finalisation in Q1 2023, after which the project will move into a bridging phase, toward ordering long lead commercial equipment. This DFS is for Phase One renewable energy and lithium production. Vulcan’s multi-disciplinary team is aiming to increase production for Phase 1 relative to previous PFS assumptions with the business to scale up as Europe’s demand for sustainable, locally sourced lithium grows.

3D seismic works in the Phase One area were successfully completed during the Quarter, to assist with refining of the field development plan. As part of its data gathering and interpretation, and towards the Phase One DFS, Vulcan is undertaking a Resource update, which is expected imminently.

Phase One: Project Execution Delivery Capability
Vulcan appointed Cris Moreno as Deputy Chief Executive Officer (Deputy CEO), effective from 1 November 2022, based in Europe. Mr. Moreno is an energy and chemicals industry executive with over 20 years’ experience in successfully delivering major capital projects, including in the lithium chemicals, cathode and LNG sectors. With unique experience in the development and execution of both LNG projects, which share many similarities in infrastructure development principles with Vulcan’s geothermal renewable energy developments, and lithium hydroxide and cathode plant projects in Europe, Mr. Moreno is well positioned to complement Vulcan’s leadership team, and is focused on developing Vulcan’s project execution delivery capability, toward Phase One execution.

To this end, Vulcan’s recruitment continues to gather momentum, focused on transitioning to a project execution company, with just around 200 personnel in-house as at 31 December. Subsequent to the end of the Quarter, Vulcan also acquired a drilling labour hire company, Comeback Personaldienstleistungen GmbH ("Comeback"), adding a further ca. 60 personnel to Vulcan’s in-house development drilling team. Vulcan is targeting operational readiness for Phase One development drilling by mid-year, with rig refurbishment progressing well.

Phase Two and future project pipeline
3D seismic survey works commenced on the ground in one of Vulcan’s planned Phase 2 lithium and geothermal energy development areas, in the Mannheim district of the Upper Rhine Valley Brine Field. These works followed prior approval of the main operating plan by the state directorate. The results will be used in feasibility studies for Phase 2, which plans to incorporate the Mannheim area. Vulcan has a renewable heat offtake agreement with MVV, the municipal energy supplier for the City of Mannheim.

Financial position
The Company remains in a strong financial position with €134.1 million cash on hand at the end of the December Quarter. The Company received revenues from Natür³Lich Insheim power plant of €1.64 million plus VAT. Cash outlays during the Quarter related to:

Phase One DFS engineering, most notably Hatch costs;
On site works of the Sorption Demo Plant and ordering of CLP Demo Plant equipment;
Natür³Lich Insheim power plant production costs;
Refurbishment of electric drill rigs; • Exploration costs and;
Corporate costs.

Additional ASX Disclosure Information
ASX Listing Rule 5.3.1: Exploration and Evaluation expenditure during the Quarter was €4.6 million. Expenditure was on engineering studies towards the Phase One DFS for the Vulcan Zero Carbon Lithium™ Project, the successful completion of 3D seismic works in Phase One area, and interpretation of seismic data. Interpretation costs include capitalised costs from VES where time was allocated to Vulcan license areas.

ASX Listing Rule 5.3.2: Development expenditure during the Quarter was €11.4 million. Expenditure related to construction of the Sorption Demo Plant, purchase of equipment for the CLP Demo Plant and refurbishment costs for Vulcan’s two electric drill rigs. Expenditure also related to design engineering costs which included capitalised costs from VEE where time was dedicated to Vulcan’s Sorption Demo

Plant.
ASX Listing Rule 5.3.3: One exploration license in the Upper Rhine Valley was granted designated Waldnerturm, increasing the Company’s license area in the Upper Rhine Valley Brine Field (URVBF) by 20.44km2. During the Quarter, Vulcan executed two agreements to expand its development footprint around its core, Phase One area. One agreement was with Geysir Europe GmbH, for the establishment of a 51:49 Joint Venture (JV) company (51% Vulcan) for a new geothermal development in the Landau-Sued license neighbouring Vulcan’s Natür3Lich Insheim operation. Vulcan’s 51% interest is contingent on execution of the first new geothermal well in the JV. Vulcan already has a brine offtake agreement with Geysir, for the existing geothermal wells and plant in the same license, which is separate to the JV. The second agreement is with Geo Exploration Technologies GmbH (“GET”), for Vulcan to develop new geothermal-lithium brine projects in the northern half of the “Rift” license also neighbouring Natür3Lich Insheim, designated “Rift Nord”. GET will retain a royalty on lithium production which will be dependent on a lithium sales pricing mechanism, and a royalty on the proceeds from the sale of electricity and district heating. Together, these agreements are designed to complement lithium-bearing geothermal brine production in Vulcan’s Phase One area around Vulcan’s Insheim license.

ASX Listing Rule 5.3.5: Payments to related parties of the Company and their associates during theQuarter per Section 6.1 of the Appendix 5B total€128,000.This is comprised of an allocation of the Managing Director remuneration of€21,000, Non-Executive Director fees of€90,000as well as consulting fees of€17,000to JRB Consulting, a company related to one of the Non-Executive Directors, in respect of a Board mandated review of the company’s ESG reporting.Please see the Remuneration Report in the 2022 Annual Report for further details on Director’s Remuneration.

Payments to related parties of the Company and their associates during theQuarter per Section 6.2 of the Appendix 5B total€82,000. This amount is an allocation of the Managing Director’s remuneration for work done on exploration activities associated with the VulcanZero CarbonLithium™Project.Please see the Remuneration Report in the 2022 Annual Report for further details on Director’s Remuneration.


Italy >>  10/7/2024 - In line with the strategy to develop solutions for the energy transition, Saipem has signed a Memorandum of Understanding with Geolog and Ignis H2 Ene...
United States >>  10/3/2024 - Sage Geosystems, a leader in next-generation geothermal using its proprietary Geopressured Geothermal Systems (GGS) technology, announced it has been ...

United Kingdom >>  10/2/2024 - Stellae Energy, a UK-based Green Energy Solutions and Assets company, is pleased to announce the signing of a detailed Memorandum of Understanding (MO...
United States >>  10/2/2024 - Texas has been at the forefront of energy regulation and innovation for more than a century, and the RRC has new proposed rules for public comment to ...

Taiwan >>  10/1/2024 - Baseload Power Taiwan is excited to announce its partnership with Taiwan Power Company (Taipower), Taiwan Cogeneration Corporation (TCC), and leading ...
United States >>  10/1/2024 - An agreement has been signed between the U.S. Department of Energy and the Utah Frontier Observatory for Research in Geothermal Energy (FORGE) to cont...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.