Weekly Drilling Report March 3, 2022
Source: www.gulfoilandgas.com 3/3/2023, Location: Europe
WELL: West Akcakoca-1
Days since move: 16
Progress: 97 metres
Measured Depth: 3137 metres
Week Summary:
RIH 9 5/8” x 9 7/5” casing to 3137 metres (current TD)
Further Activities:
Cement intermediate string of casing and wait on cement
Drill 8 ½” x 9” hole to TD of about 3760 metres
Run in and cement 7” casing
Clean borehole, perforate, test and turn over to production
Skid back over to Guluc 2 to perforate, test and turn over to production
Well drilling activities are going as expected.