WELL: Bayhanli-2
• Progress: 464 meters
• Measured Depth: 3268 metres
Week Summary:
1. Continue to drill 8 ˝” hole to 3400 metres
2. Conditions hole, run in 7” casing and cement
3. Clean borehole casing
Further Activities:
1. Continue to drill 8 ˝” hole to 3425 metres
2. Conditions hole, run in 7” casing liner hanger and cement
3. Clean borehole casing
4. Perforate, test and turn over to production department
The measured total depth is about 3425 metres with a true vertical depth of about 1200 metres. This well will take about another 1 day to drill at total depth. After TD, the well will be cased, perforated and put on production.