PetroNor is pleased to provide the following update on the Congo operations
related to the PNGF Sud field complex. The infill drilling programme, which was paused at the end of
2022 as planned following the successful drilling of six wells on the Litanzi and Tchibeli NE fields, has
restarted on the Tchibeli field.
The first infill well on Tchibeli spudded on 21 May 2023 with the drilling rig Axima. As of 9 June 2023,
the well has been drilled, logged and cased at the targeted total depth of 2,694 mMD/2,172 mTVDSS
and is about to undergo completion. Base case plans are to drill four wells in the field with first oil
estimated in August from the initial two wells. The drilling programme is planned to extend through
October.
Looking at the year-to-date period, preliminary allocations indicate that production on PNGF Sud has
remained as forecast consistently above ~30,000 bopd gross and ~5,000 bopd net. Production is
supported by the previously mentioned strong contribution from the six infill wells on Litanzi and
Tchibeli NE. This includes steady production from the Vandji exploration discovery in Tchibeli NE
whose production performance is important input to the consideration for further pre-salt
exploration and appraisal targets in the license area.
The next sale of PetroNor’s entitlement oil is scheduled in late June with an estimated lifting of 270,000
bbls bringing total sales for the year to 833,000 bbls. The previous sales realised an average price of
$78.3/bbl.
An announcement will be made following the lifting in June.