Tlou Energy Provides Drilling and Operations update

Source: www.gulfoilandgas.com 6/14/2023, Location: Africa

Ø Drilling of Lesedi 6 vertical well and lateral well top-hole sections complete
Ø Core-hole completed and coal samples acquired
Ø Overhead transmission lines 73% complete
Ø Entitlement offer remains open to eligible shareholders, partially underwritten up to A$5m

Production Wells
The Company is currently drilling the Lesedi 6 gas production pod. The pod will comprise one vertical production well (Lesedi 6P) intersected by two lateral wells (Lesedi 6A and Lesedi 6B) drilled horizontally through the target reservoir section for several hundred metres.

Lesedi 6P - Vertical Production Well
This well has been drilled to a depth of 589m and intersected 6m of the target lower Morupule coal. Well casing was cemented in place, with fiberglass casing at the target coal seam underreamed to expose the coal to the well bore to facilitate dewatering and gas flow.

Core-hole drilling
The objective of the core-hole is to provide additional geological control in the vicinity of the Lesedi 6 gas production pod.

In addition to providing coal and gas content data, the core-hole accurately determined the top and bottom of the target coal seam close to where the lateral section of Lesedi 6A and Lesedi 6B will enter the coal. This is important data for drilling of the lateral section of each well.

The core-hole was completed and logged after reaching a total depth of 535m and intersecting 6m of coal. 18 coal samples were taken and placed in desorption canisters for further analysis.

Transmission Lines
Work on the transmission lines to connect Tlou's Lesedi power project to the existing power grid is progressing. Overall progress to date is ~73%. This work is expected to be completed in 3Q23.

The 100 Km line includes planting wooden and steel pole structures. Most of the wooden poles have been erected and work has begun on the steel structures. Line stringing is also underway with ~30km of the phase conductor and ~67km of the GSW earth wire complete.

Substations
Substations are required at either end of the transmission line, one to tie Tlou's generators to the transmission line at Lesedi and another to integrate the line with the existing Botswana Power Corporation (BPC) substation at Serowe.

OptiPower, a division of Murray & Roberts Ltd has been contracted to complete this work. OptiPower has established a site in Serowe and appointed subcontractors for detailed engineering design and civils works with geotechnical assessments, soil resistivity and topographical surveys now complete. The substations are expected to be commissioned in 2Q24.

Operations and generation facility
Work is continuing on a purpose-built operations facility for the initial 10MW development and to allow for project expansion thereafter. This project is being managed by African Gas Services on behalf of Tlou and it is expected to be completed later this year.

This facility will also include the power generation site and the Company has engaged external advisors to provide technical and commercial advice relating to site based power generation design, procurement, construction and operation.

Entitlement Offer
The Company continues to source funding to develop the power project including an Entitlement Offer to eligible shareholders to raise up to a maximum of approximately A$10,645,473 (£5,855,010, BWP92,615,612). The Entitlement Offer is partially underwritten up to A$5m.


Norway >>  10/10/2024 - The Norwegian Offshore Directorate has granted Vår energi ASA drilling permit for the wells 7122/7-8 and 7122/8-3 S in production licence 229, cf. Sec...
United States >>  10/10/2024 - Zephyr Energy plc (AIM: ZPHR) (OTCQB: ZPHRF), the Rocky Mountain oil and gas company focused on responsible resource development and carbon-neutral op...

New Zealand >>  10/8/2024 - New Zealand Energy Corp. (TSXV: NZ) ("NZEC" or the "Company") is pleased to provide an operational update regarding the drilling of the Tariki-5 gas d...
Mongolia >>  10/7/2024 - Petro Matad Limited, the AIM quoted Mongolian oil company, provides the following operational update on activities in its Block XX Production Sharing ...

Canada >>  10/3/2024 - Questerre Energy Corporation reported on the upcoming drilling program at Kakwa North.

The Company plans to participate in three (1.5 net) ...

Mongolia >>  10/1/2024 - Petro Matad Limited (AIM: MATD), the AIM quoted Mongolian oil company, announces that Heron-2, the first development well to be drilled on the Petro M...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.