Signing of the Support Agreement between the Romanian State and Nuclearelectrica

Source: www.gulfoilandgas.com 6/9/2023, Location: Europe

The Support Agreement was signed between the Romanian State – the Romanian Government, the General Secretariat of the Government, the Ministry of Energy, the Ministry of Finance, the Ministry of Transport – and the National Company Nuclearelectrica, for the development of the National Strategic Project Units 3 and 4 Cernavoda NPP.

The signing of the Support Agreement between the Romanian State and Nuclearelectrica for the development of the Cernavoda NPP Units 3 and 4 Project allows the start of the activities related to Phase II of the Project, namely: the conclusion of the contracts for the development of the critical engineering necessary to update the Project; the updating of the Project budget; the structuring and contracting of the financing and the agreement of an appropriate contractual architecture for the implementation of the Project; the obtaining of the favourable opinion of the European Commission following the notification of the Project according to Art. 41 of the EURATOM Treaty and a positive decision in accordance with the relevant European provisions on State aid; Obtaining the Nuclear Safety Authorisation for the Construction phase and making the Final Investment Decision to proceed to Phase III (Construction).

“The signing of the Support Agreement between the Romanian State and Nuclearelectrica for the development of the Cernavoda NPP Units 3 and 4 Project shows the firm support of the Romanian State for the development of the Romanian nuclear programme. We thank the Romanian Presidency, the Romanian Government and Parliament, the Secretariat General of the Government, the Ministry of Energy, the Ministry of Transport, the Ministry of Finance for their involvement and support in the continuation of this project! Units 3 and 4, which are scheduled to enter commercial operation in 2030 and 2031 respectively, will add another 10TWh of clean, stable and affordable energy to the national energy system, supporting energy security. In addition, the 4 units at Cernavoda will generate about 66% of Romania’s clean energy, with an impact in achieving Romania’s decarbonisation targets. The Units 3 and 4 project is particularly important for Romania’s energy future and consumer protection and, at the same time, a source of pride for the entire Nuclearelectrica team. I congratulate and thank all colleagues involved in the project and in reaching this important milestone, as well as the entire team who contribute every day to keep the company at the highest standards of operation, nuclear safety and productivity” – Cosmin Ghita, CEO, Nuclearelectrica.

By signing the Support Agreement, the Romanian State has committed itself to take the necessary steps to finance the Cernavoda NPP Units 3 and 4 Project including through: granting state guarantees to the financiers of the project, within the framework of any intergovernmental support agreements or memoranda or outside such agreements; implementing the “Contracts for Difference” scheme and adopting administrative and/or legislative measures to ensure compliance with the technical criteria set out in the European Commission’s Complementary Delegated Act; the contribution in kind by the quantity of heavy water and uranium octoxide related to the first nuclear fuel load, cooling water for the operation of the 2 nuclear units and the completion of the electricity transmission lines necessary for the purpose of connection to the National Energy System and the discharge of the electricity produced in the 2 nuclear units.

The intention of the Romanian State and SNN, in accordance with the new project development strategy, is to carry out this project in a Euro-Atlantic consortium on the basis of the Agreement between the Government of Romania and the Government of the United States of America on cooperation in connection with nuclear power projects at Cernavoda and in the civil nuclear energy sector in Romania.

During COP 27, in November 2022, the US Exim Bank announced the issuance of two letters of interest for the financing of technical services provided by the US in connection with the Cernavoda Units 3 and 4 project, developed by the subsidiary of Societatea Na?ionala Nuclearelectrica S.A.

Based on the preliminary information presented, EXIM may consider funding up to USD 50 million from the US export contract for pre-project technical services as part of the Engineering Multiplier Program (EMP) in Phase 2 of the project. Subsequently, in Phase III of the project it may consider funding up to USD 3 billion from the US export contract for engineering and project management services for the contract to complete Units 3 and 4 of the Cernavoda nuclear power plant.

The Cernavoda NPP Units 3 and 4 project will be implemented on the basis of the Continuation Strategy, approved by SNN shareholders in 2021, in three stages, in line with international experience in nuclear power plant construction:

Stage 1, starting at the end of 2021, represents the preparatory stage, initiated by the capitalization and operationalization of the project company, Energonuclear S.A. This stage will last up to 24 months, during which time a set of engineering and safety documentation required for the Project start-up will be prepared/updated (updating of basic licensing documents, safety guidelines, project modifications related to nuclear safety, reassessment of existing civil structures, etc.), necessary for the substantiation of a preliminary investment decision.

As part of this phase, on November 25, 2021, Energonuclear S.A., the project company, signed the first contract with Candu Energy, a member of the SNC-Lavalin Group and Candu Design Authority and OEM (the original manufacturer of Candu technology) for the Project. Under the contract, CANDU Energy will provide engineering services to develop and update the documentation required for the initiation of the Project for CANDU Units 3 and 4.

Phase 2 of the Project, Preliminary Works – presented above.

Phase 3 of the Project, estimated to take 69-78 months, consists of mobilization of the site, commencement of construction, commissioning and commencement of commercial operation of Unit 3 in 2030 and Unit 4 in 2031.


Austria >>  12/6/2024 - Over 30 ‘newcomer’ countries are considering introducing nuclear power to mitigate climate change while strengthening energy security and bolstering e...
Philippines >>  12/6/2024 - As the Philippines embarks on the development of the country’s nuclear power programme, it is making progress in developing the necessary nuclear infr...

France >>  12/5/2024 - Otrera, a spin-off of the French Alternative Energies and Atomic Energy Commission (CEA) and a laureate of the France 2030 program, has successfully c...
Uzbekistan >>  12/5/2024 - The IAEA Director General has been in Uzbekistan this week as part of ongoing support to the country’s plans to harness nuclear science for its develo...

United Kingdom >>  12/4/2024 - Centrica plc (the "Company") is pleased to announce the extension of the lives of its four operational Advanced Gas-cooled Reactor ("AGR") nuclear pow...
United States >>  12/4/2024 - NANO Nuclear Energy Inc. (NASDAQ: NNE) (“NANO Nuclear” or “the Company”), a leading vertically integrated advanced nuclear technology company developi...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.