Construction of Amur Gas Processing Plant is 90.84 per cent Complete
Source: www.gulfoilandgas.com 12/7/2023, Location: Asia
The Gazprom Management Committee took note of the information about the progress of the Amur Gas Processing Plant (GPP) construction
project.
It was noted that three production trains are currently in operation and outputting commercial products at the Amur GPP.
The construction of the plant continues. The project is 90.84 per cent complete. Preparations for the beginning of start-up & commissioning operations are underway at the fourth production train, and construction & installation works are in progress at the fifth and sixth production trains.
At the same time, Gazprom continues to build the infrastructure of the residential microdistrict in the town of Svobodny for the employees of the Amur GPP and their families. Before the end of the year, the new houses will be ready for 250 more families to move in.
The Management Committee meeting also approved the Comprehensive Program for the reconstruction and re-equipment of gas and liquid hydrocarbon processing facilities of Gazprom and the Comprehensive Target Program for the reconstruction and re-equipment of automated process control systems at the facilities of Gazprom.
Both programs are synchronized with the activities aimed at Gazprom's transition to preferential use of domestic software. The documents cover the period from 2024 through 2028.