YEMEN DRILLING UPDATE

Source: www.gulfoilandgas.com 11/15/2004, Location: Middle East

The Company’s majority owned subsidiary, Comeco Petroleum, Inc. ("Comeco"), through which the Company holds a 16.785% interest in the East Shabwa Development Area in Yemen ("ESDA"), announces the results of the initial well of an appraisal and development drilling programme targeting the Basement in the Kharir Field. This well is the first of three wells planned for 2004.

The KHA-401 well spudded on 17th August 2004 reaching a total depth of 3,873 metres. The well was drilled to test the potential of the downthrown fault block at the far eastern end of the field. It was located away from the more prospective crestal area of the field in order to avoid the possibility of a secondary gas cap. The main objective of the well was to test the development of potential productive fractures at depth, over 600 metres below the top of the Basement and well below the level encountered in previous wells in to the Basement.

Both oil and gas shows were encountered and initial log results indicated that there were two thin zones of interest in the Upper Biyad Cretaceous reservoir and some 340 metres of inferred fractured Basement. The well was suspended to allow for the rig to be moved to the next location. Limited testing, due to a poor cement bond at the casing shoe, was carried out including acidisation, utilising a workover unit between 26th and 31st October 2004.

Initial interpretations of the test results of the well indicate that the well encountered reservoir but, the fracture development is inadequate to support economic production at this depth and location. It does however provide valuable information on the depth below top of Basement for the potential for water injection as an option for the required pressure maintenance planned for the full development of the structure.

Currently the well is suspended while options for side tracking the well to a shallower location are explored.

The second well in the Basement drilling programme, the KHA-402, is currently drilling an 8-1/2" section at 2,986 metres.



Norway >>  8/12/2022 - Aker BP ASA, operator of production licence 941, has concluded the drilling of wildcat well 6507/3-15.

The well was drilled about 14 km nor...

Norway >>  8/9/2022 - The Petroleum Safety Authority Norway has given Equinor consent for exploration drilling in block 6507/8 in the Norwegian Sea.

Operator: E...


Guyana >>  8/5/2022 - The drilling of the Beebei-Potaro exploratory well, located in the Kanuku licence, off the coast of Guyana, has been finished, according to Tullow Oil...
Australia >>  8/4/2022 - - 21 stages were stimulated, which is the greatest number of stimulation stages in a single well in the Beetaloo to date
- Delivered 927m of st...


Romania >>  8/4/2022 - Serinus Energy plc ("Serinus") (SEN), is pleased to announce that the drilling of the Canar-1 exploration well in Romania commenced.

...

Norway >>  8/3/2022 - The Norwegian Petroleum Directorate (NPD) has granted Equinor a drilling permit for well 6507/8-11 S in production licence PL 124.

Related Categories: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 