Eurus Starts Partial Operation of “Ashikawa Wind Farm”

Source: www.gulfoilandgas.com 1/9/2024, Location: Asia

Eurus Energy Holdings Corporation (“Eurus Energy”) announced today that Dohoku Wind Farm LLC, a group company of Eurus Energy, has completed construction of the north section (capacity: 68.8 MW) of the “Ashikawa Wind Farm” (capacity: 128.8 MW) in Toyotomi Town, Hokkaido, and its commencement of commercial operation on January 4, 2024. When the south section is completed, the “Ashikawa Wind Farm” will be the largest onshore wind farm in Japan*1.

The Wind Farm is a part of the "Dohoku Wind Power Generation Project”, which will install a total of 107 wind turbines at a total of six wind farms in the northern Hokkaido area.

While the northern Hokkaido is one of Japan’s most suitable areas for wind power generation due to its favorable wind conditions, the lack of sufficient transmission line capacity to deliver electricity to demand areas presented a challenge to development in the region. Thus, in order to promote the introduction of large-scale wind farms in the area, Eurus Energy along with partner companies established the North Hokkaido Wind Energy Transmission Corporation, which began commercial operation of government-subsidized large-scale power grid and storage battery facilities in April 2023.

The “Ashikawa Wind Farm” consists of two subsections (the north and south). 16 Siemens Gamesa Renewable Energy S.A. wind turbines with an output of 4.3 MW, one of the largest in Japan, are installed on the north section of the site. 15 of the same units will be installed on the south section, together making the “Ashikawa Wind Farm” the largest onshore wind farm in Japan as the total capacity of the 31 units will be 128.8MW.

All electricity generated will be sold to Hokkaido Electric Power Network Inc. When the south section starts operation in the spring of 2025, it is expected to generate electricity equivalent to the power consumption of approximately 94,000 average households and reduce CO2 emissions by 146,000 tons per year*2.

Eurus Energy will continue to give full consideration to environmental preservation and proceed with the construction of the south section with safety as our top priority, aiming to start commercial operation of all wind turbines. Based on our corporate philosophy of "Helping to preserve the global environment by disseminating and expanding clean energy technologies" and our corporate vision of "Develop with local communities and maintain the trust of society", Eurus Energy will continue to work on further expansion of wind power generation and contribute to global environmental conservation and the creation of a sustainable society.


Croatia (Hrvatska) >>  12/11/2024 - The Nordex Group has received its first order from Montenegro. The public utility EPCG – Elektroprivreda Crne Gore has ordered eight N163/6.X turbines...
Australia >>  12/10/2024 - Two brand new wind farms, including one of the largest in Victoria, are now online and generating enough affordable, reliable renewable energy to powe...

Germany >>  12/10/2024 - Energiekontor AG (“Energiekontor”), one of the leading German project developers and operators of wind and solar parks, based in Bremen and listed in ...
Netherlands/Holland >>  12/10/2024 - RWE and TotalEnergies have selected the port of Eemshaven in the northern Dutch province of Groningen as the base for turbine assembly and constructio...

Taiwan >>  12/10/2024 - Ørsted has signed an agreement with Cathay Life Insurance, the leading insurance company in Taiwan, and its affiliate Cathay Wind Power Holdings Co., ...
United Kingdom >>  12/10/2024 - Thirteen organisations across England, Wales and Scotland are set to share nearly £5m in funding through the initial round of The Crown Estate’s innov...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.