3/17/2023 - WELL: West Akcakoca-1 Days since move: 29 Progress: 115 metres Measured Depth: 3839 metres Week Summary: Drill 8 ½” x 9” hole to 3839 TD Evaluated the Logging wh... |
3/13/2023 - UK Oil & Gas PLC (UKOG) is pleased to announce that construction of Pinarova-1's drilling pad and access road commenced on schedule over the weekend. As per the Company's Pinarova-1 release of 1st Mar... |
3/10/2023 - WELL: West Akcakoca-1 • Days since move: 23 • Progress: 587 metres • Measured Depth: 3724 metres Week Summary: 1. Drill 8 ½” x 9” hole to 3724 Further Activities... |
3/3/2023 - WELL: West Akcakoca-1 Days since move: 16 Progress: 97 metres Measured Depth: 3137 metres Week Summary: RIH 9 5/8” x 9 7/5” casing to 3137 metres (current TD) ... |
3/1/2023 - UK Oil & Gas PLC (London AIM: UKOG) is pleased to announce that the Resan JV (UKOG 50% non-operated interest) having secured a suitable small rig to drill the new Pinarova-1 shallow oil exploration we... |
2/24/2023 - WELL: West Akcakoca-1 • Days since move: 9 • Progress: 1990 metres • Measured Depth: 3040 metres Week Summary: 1. Drill 12 ¼” x 13” hole to 3040 metres Further A... |
2/17/2023 - WELL: West Akcakoca-1 Days since move: 3 Progress: 48 metres Measured Depth: 1050 metres Week Summary: RIH completion string in Guluc 2 with 3 well tractors; howe... |
2/14/2023 - Trillion Energy International Inc. is pleased to provide a progress update on the Guluc 2 and West Akcakoca 1 wells at the SASB Gas field, Black Sea Turkiye. Guluc-2 is the third well in our... |
2/10/2023 - WELL: Guluc-2 • Spudded December 10, 2022. Days since spud: 61 • Progress: 0 • Measured Depth: 3910 metres Week Summary: 1. RIH with casing scraper to prepare borehole fo... |
2/3/2023 - WELL: Guluc-2 Spudded December 10, 2022. Days since spud: 53 Progress: 0 Measured Depth: 3910 metres Week Summary: Run in the 7” casing Cement the casing and... |
1/27/2023 - WELL: Guluc-2 • Spudded December 10, 2022. Days since spud: 47 • Progress: 711 metres • Measured Depth: 3910 metres Week Summary: 1. Tag Cement 3192 metres and drill out ... |
1/20/2023 - WELL: Guluc-2 Spudded December 10, 2022. Days since spud: 40 Progress: 0 Measured Depth: 3199 metres Week Summary: RIH with BHA and tag cement at 2610 Perf... |
1/13/2023 - WELL: Guluc-2 • Spudded December 10, 2022. Days since spud: 33 • Progress: 0 • Measured Depth: 3199 metres Week Summary: 1. Recover fish from 3198 metres depth – 29 met... |
1/6/2023 - WELL: Guluc-2 Spudded December 10, 2022. Days since spud: 26 Progress: 1404 metres Measured Depth: 3199 metres Week Summary: Drill 12 ¼” x 13” hole to 3199 metres – RO... |
12/30/2022 - WELL: Guluc-2 Spudded December 10, 2022. Days since spud: 20 Progress: 1795 metres Measured Depth: 2803 metres Week Summary: Drill out plugs Dri... |
12/23/2022 - WELL: Guluc-2 Spudded December 10, 2022. Days since spud: 13 Week Summary: RIH 13 3/8” casing Cement to surface and wait on cement (WOC) Test smart tools and pr... |
12/16/2022 - WELL: Guluc-2 • Spudded December 10, 2022. Days since spud: 6 Week Summary: 1. Skid the rig on to Guluc-2 2. Spud Guluc-2 well on December 10th, 2022 3. Drilled 17 ½” ... |
12/12/2022 - Trillion Energy International Inc. is pleased to have commenced Guluc-2 at the SASB natural gas field, Black Sea, after completing West Akcakoca-1 17 ½” diameter section to 1,008 metres depth. |
12/9/2022 - WELL: West Akcakoca-1 Spudded November 26, 2022. Days since spud: 13 Week Summary: - Drilled 17 ½” section to planned depth, 1008 measured depth (MD). The well inclination is 6... |
12/2/2022 - WELL: West Akcakoca-1 Spudded November 26, 2022. Days since spud: 5 Week Summary: Uranus Rig repositioned on the northern side of Akcakoca Platform West Akcakoca-1 w... |