Drilling News in Turkey

Weekly Drilling Report March 16, 2022
3/17/2023 - WELL: West Akcakoca-1
Days since move: 29
Progress: 115 metres
Measured Depth: 3839 metres

Week Summary:
Drill 8 ½” x 9” hole to 3839 TD
Evaluated the Logging wh...
UKOG Announce that Construction of Pinarova-1's Drilling Pad Commenced
3/13/2023 - UK Oil & Gas PLC (UKOG) is pleased to announce that construction of Pinarova-1's drilling pad and access road commenced on schedule over the weekend. As per the Company's Pinarova-1 release of 1st Mar...
Weekly Drilling Report March 10, 2022
3/10/2023 - WELL: West Akcakoca-1
• Days since move: 23
• Progress: 587 metres
• Measured Depth: 3724 metres

Week Summary:
1. Drill 8 ½” x 9” hole to 3724

Further Activities...
Weekly Drilling Report March 3, 2022
3/3/2023 - WELL: West Akcakoca-1
Days since move: 16
Progress: 97 metres
Measured Depth: 3137 metres

Week Summary:
RIH 9 5/8” x 9 7/5” casing to 3137 metres (current TD)

...
UK Oil & Gas Provides Update on Pinarova-1 Well
3/1/2023 - UK Oil & Gas PLC (London AIM: UKOG) is pleased to announce that the Resan JV (UKOG 50% non-operated interest) having secured a suitable small rig to drill the new Pinarova-1 shallow oil exploration we...
Weekly Drilling Report February 24, 2022
2/24/2023 - WELL: West Akcakoca-1
• Days since move: 9
• Progress: 1990 metres
• Measured Depth: 3040 metres

Week Summary:
1. Drill 12 ¼” x 13” hole to 3040 metres

Further A...
Weekly Drilling Report February 17, 2022
2/17/2023 - WELL: West Akcakoca-1

Days since move: 3
Progress: 48 metres
Measured Depth: 1050 metres

Week Summary:
RIH completion string in Guluc 2 with 3 well tractors; howe...
Trillion Energy Commences Drilling West Akcakoca Well Lateral Selection & Updates
2/14/2023 - Trillion Energy International Inc. is pleased to provide a progress update on the Guluc 2 and West Akcakoca 1 wells at the SASB Gas field, Black Sea Turkiye.

Guluc-2 is the third well in our...
Weekly Drilling Report February 9, 2022
2/10/2023 - WELL: Guluc-2
• Spudded December 10, 2022. Days since spud: 61
• Progress: 0
• Measured Depth: 3910 metres

Week Summary:
1. RIH with casing scraper to prepare borehole fo...
Weekly Drilling Report February 12, 2022
2/3/2023 - WELL: Guluc-2

Spudded December 10, 2022. Days since spud: 53
Progress: 0
Measured Depth: 3910 metres

Week Summary:
Run in the 7” casing
Cement the casing and...
Weekly Drilling Report January 26, 2022
1/27/2023 - WELL: Guluc-2
• Spudded December 10, 2022. Days since spud: 47
• Progress: 711 metres
• Measured Depth: 3910 metres

Week Summary:
1. Tag Cement 3192 metres and drill out ...
Weekly Drilling Report January 19, 2022
1/20/2023 - WELL: Guluc-2

Spudded December 10, 2022. Days since spud: 40
Progress: 0
Measured Depth: 3199 metres

Week Summary:
RIH with BHA and tag cement at 2610
Perf...
Weekly Drilling Report January 12, 2022
1/13/2023 - WELL: Guluc-2
• Spudded December 10, 2022. Days since spud: 33
• Progress: 0
• Measured Depth: 3199 metres

Week Summary:
1. Recover fish from 3198 metres depth – 29 met...
Weekly Drilling Report January 5, 2022
1/6/2023 - WELL: Guluc-2
Spudded December 10, 2022. Days since spud: 26
Progress: 1404 metres
Measured Depth: 3199 metres

Week Summary:
Drill 12 ¼” x 13” hole to 3199 metres – RO...
Weekly Drilling Report December 28, 2022
12/30/2022 - WELL: Guluc-2

Spudded December 10, 2022. Days since spud: 20

Progress: 1795 metres

Measured Depth: 2803 metres

Week Summary:

Drill out plugs
Dri...
Weekly Drilling Report December 23, 2022
12/23/2022 - WELL: Guluc-2

Spudded December 10, 2022. Days since spud: 13

Week Summary:
RIH 13 3/8” casing
Cement to surface and wait on cement (WOC)
Test smart tools and pr...
Weekly Drilling Report
12/16/2022 - WELL: Guluc-2
• Spudded December 10, 2022. Days since spud: 6

Week Summary:
1. Skid the rig on to Guluc-2
2. Spud Guluc-2 well on December 10th, 2022
3. Drilled 17 ½” ...
Trillion Energy Commences New Wells In Its Multi-Well Program
12/12/2022 - Trillion Energy International Inc. is pleased to have commenced Guluc-2 at the SASB natural gas field, Black Sea, after completing West Akcakoca-1 17 ½” diameter section to 1,008 metres depth.
Trillion Energy Announces Weekly Drilling Report
12/9/2022 - WELL: West Akcakoca-1
Spudded November 26, 2022. Days since spud: 13

Week Summary:
- Drilled 17 ½” section to planned depth, 1008 measured depth (MD). The well inclination is 6...
Weekly Drilling Report December 1, 2022
12/2/2022 - WELL: West Akcakoca-1

Spudded November 26, 2022. Days since spud: 5

Week Summary:
Uranus Rig repositioned on the northern side of Akcakoca Platform
West Akcakoca-1 w...

Artificial Lift Cementing, Stimulation Directional Drilling Drilling Drilling Engineering & Equipment Systems Enhanced Oil Recovery General Logging, Perforating, Testing Offshore Drilling Reservoir/Completion Consultants Workover & Well Services Workover Rigs/Services
For Buyers
For Suppliers
Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.