Gas sweetening News

SP13; 56 MCM Sour Gas to be Sweetened
Iran >> 1/14/2019 - Director of phase13, PayyamMotamed, announced that this project will start to produce 56 MCM of sweet gas a day in mid-February. As the latest activities on a 32-inch pipeline to onshore completedby t...
SP13; 3rd Sweetening Train to Be Operational
Iran >> 9/28/2018 - The 3rd sweetening train will be operational in a few days, managing director announced. As scheduled, the last sweetening train of the phase 13 will be also operated by October 20, Mohammad Meshkinfa...
South Pars Phase 13; Second Sweetening Row Launched
Iran >> 5/26/2018 - After pre-commissioning and commissioning tests, the second sweetening row of phase 13 was launched. The row has been now put into operation with daily production of 7 MCM of gas. Gradually it will r...
RIPI & Germany's Raschig Strike NDA
Iran >> 5/8/2018 - Iran's Research Institute of Petroleum Industry and Germany's Raschig have signed a non-disclosure agreement about gas sweetening with amine solution. ...
SP13 refinery: Gas Injection to Grid Started
Iran >> 4/7/2018 - The first sweetening row of SP13 refinery, on the anniversary of nationalization of Iranian oil industry, was put into the operation by injecting sweet gas to the sixth line of the grid. ...
Sweet Gas Injected from South Pars Phase 13 into the National Trunkline
Iran >> 4/4/2018 - The first gas sweetening unit in South Pars Phase 13 started operation on March 20, 2018. The utility started operation on the anniversary of nationalization of Iran’s oil industry, receiving 7 millio...
1st Sweetening Facility of SP Phases 22-24 Ready to Operate
Iran >> 3/3/2018 - The first gas sweetening facility in phases 22, 23 and 24 of the giant South Pars Gas Field has come online and is ready to intake sour gas from the field, said the operator for phases’ development pl...
IOOC Signs €800m Deal with Domestic Firm
Iran >> 10/8/2017 - The Iranian Offshore Oil Company (IOOC) has signed a deal worth 800 million Euros with an Iranian company to complete a number of IOOC projects. ...
SP2&3 Starts Constructing First Condensate Sweetening Unit
Iran >> 8/26/2017 - Construction project of gas condensate de-mercapitanization (DMC) unit began in SP 2&3. A contract was concluded between National Iranian Oil Company (NIOC) and Research Institute of Petroleum Industr...
Phases 20 & 21 Second Row of Sweetening Ready for Gas
Iran >> 12/4/2016 - The second sweetening row of the phases 20 & 21 refinery is operationalized and ready for the gas receipt from South Pars field phase 21 platform. ...
Total Sweet Gas Recovery from Phase 12 at 12bcm
Iran >> 9/6/2015 - The total sweet gas recovered from Phase 12 development of the supergiant South Pars Gas field stands at 16 billion cubic meters, operator of the phases said. ...
Iran Develops Sour Gas Sweetening Solvent
Iran >> 2/27/2015 - Iran has managed to produce a much-needed solvent used in sour gas sweetening process, director of research and technology at National Iranian Gas Company said. ...
Phase 12 to be Officially Launched by Late Feb. 2015
Iran >> 2/6/2015 - Phase 12 of the supergiant South Pars gas field is will be fully operational by the time the 6th gas sweetening unit of the phase’s refinery comes online and the massive refinery becomes fully operati...
New Duvernay Gathering Pipeline to the KA Plant
Canada >> 12/18/2013 - SemCAMS, a subsidiary of SemGroup(R) Corporation (SEMG), announced that it will extend its capture area into the Duvernay region through the construction of the low sour gas gathering line, to be name...
GPS Secures PDO Lekhwair Development Contract
Oman >> 3/22/2012 - Global Process Systems (GPS), a global provider of technology-based "design and build" process facilities solutions for the upstream oil & gas industry, has won a contract to supply gas-sweetening and...
GPS Dubai Wins Milestone Project with Larsen & Toubro
GPS Dubai Wins Milestone Project with Larsen & Toubro Oman >> 2/29/2012 - Larsen & Toubro Ltd of India has awarded GPS Dubai the contract to supply of Gas Sweetening and Gas Dehydration process systems required for the Lekhwair Gas Field Development (LGFD) Project in Oman. ...
KNPC & Tecnimont Sign Acid Gas Removal Contract
Kuwait >> 9/6/2010 - Kuwait National Petroleum Company (KNPC) signed a 117 million-Kuwaiti-dinar (407 million US dollar) contract with Italy's Maire Tecnimont SpA for an acid gas removal project at the Mina Al- Ahmadi ref...
Petrofac Wins Qatar Petroleum Contract Worth $600 m
Qatar >> 3/29/2010 - Petrofac, the international oil & gas facilities service provider, has been awarded a contract worth more than US$600 million for a gas sweetening facilities project in Qatar’s Messaieed and Dukhan in...
GS E&C Consortium Awarded 1.24 Billion-Gas Project
Iran >> 10/13/2009 - GS E&C consortium was awarded EUR1.24 billion Iran GAS Sweetening project as an EPC contractor, and this project is located next to SP 9~10 project site. POGC is constructing a new Gas Sweetening proj...
Award of Karachaganak Phase III Feed
Kazakhstan >> 6/25/2007 - Petrofac has received a letter of award from Karachaganak Petroleum Operating BV (KPO) for a Front-End Engineering and Design (FEED) study for Phase III of the development of the Karachaganak Processi...

Gas dehydration Gas sweetening Gas Treating General GTL Processing LNG Processing LPG Domestic use LPG Odorless Packing Phase Separation Scrubbers
For Buyers
For Suppliers
Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.