4/16/2015 - Petroleum and energy minister Tord Lien is opening the Valemon gas and condensate field in the North Sea. Expected recoverable reserves from the field are 192 million barrels of oil equivalent. ... |
4/14/2015 - The 22 000 tonnes topside for the new offshore platform for the Edvard Grieg field is ready for delivery, in line with the contract awarded three years ago. Hence, the project is in an exceptional cas... |
3/13/2015 - Statoil awarded the contract for offshore facility services on the Statfjord and Snorre fields to Coor Service Management. The contract is worth roughly NOK 1.1 billion over a 5-year period. The contr... |
3/9/2015 - Claxton, an Acteon company, has been awarded a contract with Statoil to supply conductor and internal centralizers to a minimum of 14 wells on the Gina Krog development, offshore Norway. The contract ... |
3/8/2015 - Drydocks World the international service provider to the shipping, offshore, oil, gas and energy sectors has been awarded the contract from Kvaerner to carry out the fabrication of components on the J... |
3/2/2015 - Statoil has signed a contract with Allseas for installation of three platform topsides on the Johan Sverdrup field. The vessel will be installing the topsides for the drilling, processing and living q... |
2/24/2015 - Statoil, on behalf of the Johan Sverdrup partnership, will sign a contract with Aibel for the construction of the deck for the drilling platform on the field. The contract is worth in excess of NOK 8 ... |
2/24/2015 - Wood Group Mustang Norway (WGMN), together with Statoil, has successfully completed hook-up of the Valemon platform in the North Sea on schedule. Valemon, located on the Norwegian continental shelf (N... |
2/18/2015 - At the start of this year, Holmatro and its Norwegian dealer EIVA-SAFEX AS jointly supplied 64 cylinders, each with a capacity of 536 tons, to the tension-leg platform (TLP) Snorre A. Besides cylinder... |
2/9/2015 - Statoil and its licence partners have chosen an unmanned wellhead platform as the concept for the Oseberg Future development phase I project in the North Sea. The platform will be controlled from the ... |
1/20/2015 - Kvaerner has signed the final contract for delivery of the steel jacket substructure for the riser platform at the Johan Sverdrup field. Since the letter of intent for the delivery was signed in June ... |
9/3/2014 - Huldra is the first gravity-based, Statoil-operated installation in the North Sea to be shut down permanently. Terminating production on 3 September, the platform has produced gas and condensate for s... |
8/26/2014 - Aasta Hansteen and Polarled are moving the boundaries for technology, deep waters and ripple effects on the Norwegian continental shelf (NCS). ... |
8/20/2014 - Statoil shut down production on the Troll C platform in the North Sea on Sunday 17 August after an inspection programme on the platform detected corrosion damage to a pipe connected to the oil export ... |
8/19/2014 - Norwegian prime minister Erna Solberg officially opened the Gudrun platform in the North Sea, 19 August. This is the first new Statoil-operated platform on the Norwegian continental shelf (NCS) since ... |
8/15/2014 - Kvaerner and KBR, Inc announced they will establish a joint venture to competitively bid on offshore platform topsides contracts for the Johan Sverdrup field development offshore Norway. The alliance ... |
8/13/2014 - AF Decom Offshore U.K. Limited in a consortium with Heerema Marine Contractors Nederland SE, has been awarded a Letter of Intent for the removal and disposal of the Murchison Platform in the North Sea... |
7/28/2014 - The topsides were lifted into place on the steel jacket on the Valemon field in the North Sea. Produced by Samsung Heavy Industries this is the first Statoil topsides built in South Korea. The structu... |
7/15/2014 - VARD has secured a contract for the design and construction of one Platform Supply Vessel for E.R. Offshore. The vessel is a multifunctional PSV of VARD 1 08 design with a total length of 81 meters, b... |
6/26/2014 - Statoil enters into a frame agreement with Kvaerner for the delivery of jackets for the North Sea in the period up to 2020. At the same time, the companies will sign a letter of intent for the deliver... |